It is agreed during the summit we should write down such document. Here is my attempt of doing so.

We should probably commit something like this into xen.git so that it gets updated regularly.

Comments are welcome.

-----

% Xen Release Management
% Wei Liu <<[email protected]>>
% Revision 1

# Motivation

Over the years we have had different people from different company signning up as the Release Manager of Xen. It would be rather wasteful if every new Release Manager has to go over everything and tripped over by the same mistakes again and again.

This file intends to document the process of managing a Xen release. It is mainly written for Release Manager, but other roles (contributors, maintainers and committers) are also encouraged to read this document, so that they can have an idea what to expect from the Release Manager.

# Xen release cycle

The Xen hypervisor project now releases twice a year, at the beginning of June and the beginning of December. The actual release date depends on a lot of factors.

We can roughly divide one release into two periods. The development period and the freeze period. The former is 4 months long and the latter is about 2 months long.

During development period, contributors submit patches to be reviewed and committed into xen.git.

During freeze period, the tree is closed for new features. Only bug fixes are accepted. This period can be shorter or longer than 2 months. If it ends up longer than 2 months, it eats into the next development period.

# The different roles in a Xen release

## Release Manager

A trusted developer in the community that owns the release process. The major goal of the Release Manager is to make sure a Xen release has high quality and doens't slip too much.

The Release Manager will not see much workload during development period, but expects to see increasing workload during the freeze period until the final release. He or she is expected to keep track of issues, arrange RCs, negotiate with relevant stakeholders, balance the need from various parties and make difficult decisions when necessary.

The Release Manager essentially owns xen-unstable branch during the freeze period. The committers will act on the wishes of the Release Manager during that time.

## Maintainers

A group of trusted developers who are responsible for certain components in xen.git. They are expected to respond to patches / questions with regard to their components in a timely manner, especially during the freeze period.

## Committers

A group of trusted maintainers who can commit to xen.git. During the development window they normally push things as they see fit. During the freeze period they transfer xen-unstable branch ownership and act on the wishes of the Release Manager. That normally means they need to have an Release Ack in order to push a patch.

## Contributors

Contributors are also expected to respond quickly to any issues regarding the code they submitted during development period. Failing that, the Release Manager might decide to revert the changes, declare feature unsupported or take any action he / she deems appropriate.

## The Security Team

The Security Team operates independently. The visibility might be rather limited due to the sensitive nature of security work. The best action the Release Manager can take is to set aside some time for potential security issues to be fixed.

## The Release Technician

The Release Technician is the person who tags various trees, prepares tarball etc. He or she acts on the wishes of the Release Manager. Please make sure the communication is as clear as it can be.

## The Community Manager

The Community Manager owns xenproject.org infrastructure. He or she is responsible for updating various web archives, updating wiki pages and coordinating with the PR Personnel.

## The PR Personnel

They are responsible for corrdinating with external reporters to publish Xen release announcement. The Release Manager should be absolutely sure the release is going out on a particular date before giving them the signal to proceed, because there is a point of no return once they schedule a date with external reporters.

# What happens during a release

## Development period

Send out monthly update email. The email contains the timeline of the release, the major work items and any other information the Release Manager sees fit. Please consider adding a recurring event to your calendar.

Occasionally check the status of the xen-unstable branch, make sure it gets timely pushes to master.

## Freeze period

Before or at very early stage of the freeze period, agree with the Community Manager a schedule for RC test days.

Once the freeze starts, the ownership of xen-unstable branch automatically transfers to the Release Manager.

Here is a list of things to do for making RCs:

1. Check the status of the tree. Ask the Release Technician to make an RC if the tree is good.

1. Send an email to xen-devel, xen-users and xen-announce to announce the RC.

1. Branch and / or reopen the tree for further feature submission if appropriate.

1. Collect and track any issues reported, determine their severity, prod relevant developers and maintainers to fix the issues.

1. When patches to fix issues are posted, determine if the patches are good to be included.

1. Go back to 1.

It is normally OK in the early RCs that you hand back xen-unstable branch to committers so that they can commit bug fixes at will. As we approach late RCs, the standard for accepting a patch will get higher and higher. Please communicate clearly when committers can commit at will and when formal Release Ack is needed.

At the same time, work with the Community Manager, PR Personnel and Contributors to gather a list of features for the release. Discuss the support status of new features with stakeholders. Help prepare the press release, write a blog post for the release.

When you think all pending issues are fixed and Xen is ready to be released from the last RC:

1. Send out commit moratorium emails to committers@.

1. Check all the trees (mini-os, qemu-trad, qemu-xen, seabios, ovmf etc). They have the correct commits and all security patches applied. There will be tools provided.

1. Ask the Community Manager and Release Technician to double-check all security patches have been applied. If not, apply them, arrange another RC and restart this checklist.

1. Ask the Release Technician to tag the trees and make the tarball. Ask the Community Manager to update relevant web assets.

1. Give the PR Personnel signal to proceed. Cooridinate with him / her on the public annoucement.

1. Make the announcement on various mailing list, publish the blog post.

Allow for contigencies. It is not uncommon that some last minute (security or not) bugs are discovered. To provide a fix takes time, the test of the fix will also take time. Allow for at least 1 week from getting a fix to getting a push. For security bugs, corrdinate with the Security Team to adjust the dates according to our security policy.

# Email templates

## RC emails

Quoted 12 lines

Hi all,

Xen X.Y rcZ is tagged. You can check that out from xen.git:

git://xenbits.xen.org/xen.git X.Y.0-rcZ

For your convenience there is also a tarball at:
https://downloads.xenproject.org/release/xen/X.Y.0-rcZ/xen-X.Y.0-rcZ.tar.gz

And the signature is at:
https://downloads.xenproject.org/release/xen/X.Y.0-rcZ/xen-X.Y.0-rcZ.tar.gz.sig

Quoted 7 lines

Please send bug reports and test reports to [email protected]. When sending bug reports, please CC relevant maintainers and me ([email protected]).

As a reminder, there will be another Xen Test Day.

See instructions on: URL_TO_TEST_INSTRUCTIONS

_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xen.org/xen-devel

#1 lore raw
Quoted 10 lines · Wei Liu

It is agreed during the summit we should write down such document. Here is my attempt of doing so.

We should probably commit something like this into xen.git so that it gets updated regularly.

Comments are welcome.

-----

Quoted 7 lines

% Xen Release Management
% Wei Liu <<[email protected]>>
% Revision 1

# Motivation

Over the years we have had different people from different company signning

signing

Quoted 80 lines

up as the Release Manager of Xen. It would be rather wasteful if every new Release Manager has to go over everything and tripped over by the same mistakes again and again.

This file intends to document the process of managing a Xen release. It is mainly written for Release Manager, but other roles (contributors, maintainers and committers) are also encouraged to read this document, so that they can have an idea what to expect from the Release Manager.

# Xen release cycle

The Xen hypervisor project now releases twice a year, at the beginning of June and the beginning of December. The actual release date depends on a lot of factors.

We can roughly divide one release into two periods. The development period and the freeze period. The former is 4 months long and the latter is about 2 months long.

During development period, contributors submit patches to be reviewed and committed into xen.git.

During freeze period, the tree is closed for new features. Only bug fixes are accepted. This period can be shorter or longer than 2 months. If it ends up longer than 2 months, it eats into the next development period.

# The different roles in a Xen release

## Release Manager

A trusted developer in the community that owns the release process. The major goal of the Release Manager is to make sure a Xen release has high quality and doens't slip too much.

The Release Manager will not see much workload during development period, but expects to see increasing workload during the freeze period until the final release. He or she is expected to keep track of issues, arrange RCs, negotiate with relevant stakeholders, balance the need from various parties and make difficult decisions when necessary.

The Release Manager essentially owns xen-unstable branch during the freeze period. The committers will act on the wishes of the Release Manager during that time.

## Maintainers

A group of trusted developers who are responsible for certain components in xen.git. They are expected to respond to patches / questions with regard to their components in a timely manner, especially during the freeze period.

## Committers

A group of trusted maintainers who can commit to xen.git. During the development window they normally push things as they see fit. During the freeze period they transfer xen-unstable branch ownership and act on the wishes of the Release Manager. That normally means they need to have an Release Ack in order to push a patch.

## Contributors

Contributors are also expected to respond quickly to any issues regarding the code they submitted during development period. Failing that, the Release Manager might decide to revert the changes, declare feature unsupported or take any action he / she deems appropriate.

## The Security Team

The Security Team operates independently. The visibility might be rather limited due to the sensitive nature of security work. The best action the Release Manager can take is to set aside some time for potential security issues to be fixed.

## The Release Technician

The Release Technician is the person who tags various trees, prepares tarball etc. He or she acts on the wishes of the Release Manager. Please make sure the communication is as clear as it can be.

## The Community Manager

Quoted 7 lines

The Community Manager owns xenproject.org infrastructure. He or she is responsible for updating various web archives, updating wiki pages and coordinating with the PR Personnel.

## The PR Personnel

They are responsible for corrdinating with external reporters to publish Xen

coordinating

Quoted 30 lines

release announcement. The Release Manager should be absolutely sure the release is going out on a particular date before giving them the signal to proceed, because there is a point of no return once they schedule a date with external reporters.

# What happens during a release

## Development period

Send out monthly update email. The email contains the timeline of the release, the major work items and any other information the Release Manager sees fit. Please consider adding a recurring event to your calendar.

Occasionally check the status of the xen-unstable branch, make sure it gets timely pushes to master.

## Freeze period

Before or at very early stage of the freeze period, agree with the Community Manager a schedule for RC test days.

Once the freeze starts, the ownership of xen-unstable branch automatically transfers to the Release Manager.

Here is a list of things to do for making RCs:

1. Check the status of the tree. Ask the Release Technician to make an RC if the tree is good.

1. Send an email to xen-devel, xen-users and xen-announce to announce the RC.

Quoted 7 lines

1. Branch and / or reopen the tree for further feature submission if appropriate.

1. Collect and track any issues reported, determine their severity, prod relevant developers and maintainers to fix the issues.

1. When patches to fix issues are posted, determine if the patches are good to be included.

1. Go back to 1.

To which 1.? There are plenty to choose from. :-D

Quoted 24 lines

It is normally OK in the early RCs that you hand back xen-unstable branch to committers so that they can commit bug fixes at will. As we approach late RCs, the standard for accepting a patch will get higher and higher. Please communicate clearly when committers can commit at will and when formal Release Ack is needed.

At the same time, work with the Community Manager, PR Personnel and Contributors to gather a list of features for the release. Discuss the support status of new features with stakeholders. Help prepare the press release, write a blog post for the release.

When you think all pending issues are fixed and Xen is ready to be released from the last RC:

1. Send out commit moratorium emails to committers@.

1. Check all the trees (mini-os, qemu-trad, qemu-xen, seabios, ovmf etc). They have the correct commits and all security patches applied. There will be tools provided.

1. Ask the Community Manager and Release Technician to double-check all security patches have been applied. If not, apply them, arrange another RC and restart this checklist.

Quoted 7 lines

1. Ask the Release Technician to tag the trees and make the tarball. Ask the Community Manager to update relevant web assets.

1. Give the PR Personnel signal to proceed. Cooridinate with him / her on the public annoucement.

1. Make the announcement on various mailing list, publish the blog post.

use other item numbers than only 1. :-)

Quoted 8 lines

Allow for contigencies. It is not uncommon that some last minute (security or not) bugs are discovered. To provide a fix takes time, the test of the fix will also take time. Allow for at least 1 week from getting a fix to getting a push. For security bugs, corrdinate with the Security Team to adjust the dates according to our security policy.

Quoted 24 lines

# Email templates

## RC emails

Quoted 19 lines

Hi all,

Xen X.Y rcZ is tagged. You can check that out from xen.git:

git://xenbits.xen.org/xen.git X.Y.0-rcZ

For your convenience there is also a tarball at:
https://downloads.xenproject.org/release/xen/X.Y.0-rcZ/xen-X.Y.0-rcZ.tar.gz

And the signature is at:
https://downloads.xenproject.org/release/xen/X.Y.0-rcZ/xen-X.Y.0-rcZ.tar.gz.sig

Please send bug reports and test reports to [email protected]. When sending bug reports, please CC relevant maintainers and me ([email protected]).

As a reminder, there will be another Xen Test Day.

See instructions on: URL_TO_TEST_INSTRUCTIONS

Thanks,

Juergen

_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xen.org/xen-devel

author
#2 lore raw
Quoted 15 lines · Juergen Gross
Quoted 14 lines · Wei Liu

It is agreed during the summit we should write down such document. Here is my attempt of doing so.

We should probably commit something like this into xen.git so that it gets updated regularly.

Comments are welcome.

-----

% Xen Release Management
% Wei Liu <<[email protected]>>
% Revision 1

Quoted 6 lines
Quoted 3 lines

# Motivation

Over the years we have had different people from different company signning

signing

Fixed.

And I also realised I shouldn't have written "company" because I don't want to imply one has to be employed by a company to become RM.

Quoted 84 lines
Quoted 84 lines

up as the Release Manager of Xen. It would be rather wasteful if every new Release Manager has to go over everything and tripped over by the same mistakes again and again.

This file intends to document the process of managing a Xen release. It is mainly written for Release Manager, but other roles (contributors, maintainers and committers) are also encouraged to read this document, so that they can have an idea what to expect from the Release Manager.

# Xen release cycle

The Xen hypervisor project now releases twice a year, at the beginning of June and the beginning of December. The actual release date depends on a lot of factors.

We can roughly divide one release into two periods. The development period and the freeze period. The former is 4 months long and the latter is about 2 months long.

During development period, contributors submit patches to be reviewed and committed into xen.git.

During freeze period, the tree is closed for new features. Only bug fixes are accepted. This period can be shorter or longer than 2 months. If it ends up longer than 2 months, it eats into the next development period.

# The different roles in a Xen release

## Release Manager

A trusted developer in the community that owns the release process. The major goal of the Release Manager is to make sure a Xen release has high quality and doens't slip too much.

The Release Manager will not see much workload during development period, but expects to see increasing workload during the freeze period until the final release. He or she is expected to keep track of issues, arrange RCs, negotiate with relevant stakeholders, balance the need from various parties and make difficult decisions when necessary.

The Release Manager essentially owns xen-unstable branch during the freeze period. The committers will act on the wishes of the Release Manager during that time.

## Maintainers

A group of trusted developers who are responsible for certain components in xen.git. They are expected to respond to patches / questions with regard to their components in a timely manner, especially during the freeze period.

## Committers

A group of trusted maintainers who can commit to xen.git. During the development window they normally push things as they see fit. During the freeze period they transfer xen-unstable branch ownership and act on the wishes of the Release Manager. That normally means they need to have an Release Ack in order to push a patch.

## Contributors

Contributors are also expected to respond quickly to any issues regarding the code they submitted during development period. Failing that, the Release Manager might decide to revert the changes, declare feature unsupported or take any action he / she deems appropriate.

## The Security Team

The Security Team operates independently. The visibility might be rather limited due to the sensitive nature of security work. The best action the Release Manager can take is to set aside some time for potential security issues to be fixed.

## The Release Technician

The Release Technician is the person who tags various trees, prepares tarball etc. He or she acts on the wishes of the Release Manager. Please make sure the communication is as clear as it can be.

## The Community Manager

The Community Manager owns xenproject.org infrastructure. He or she is responsible for updating various web archives, updating wiki pages and coordinating with the PR Personnel.

Quoted 6 lines
Quoted 3 lines

## The PR Personnel

They are responsible for corrdinating with external reporters to publish Xen

coordinating

Fixed.

Quoted 32 lines
Quoted 32 lines

release announcement. The Release Manager should be absolutely sure the release is going out on a particular date before giving them the signal to proceed, because there is a point of no return once they schedule a date with external reporters.

# What happens during a release

## Development period

Send out monthly update email. The email contains the timeline of the release, the major work items and any other information the Release Manager sees fit. Please consider adding a recurring event to your calendar.

Occasionally check the status of the xen-unstable branch, make sure it gets timely pushes to master.

## Freeze period

Before or at very early stage of the freeze period, agree with the Community Manager a schedule for RC test days.

Once the freeze starts, the ownership of xen-unstable branch automatically transfers to the Release Manager.

Here is a list of things to do for making RCs:

1. Check the status of the tree. Ask the Release Technician to make an RC if the tree is good.

1. Send an email to xen-devel, xen-users and xen-announce to announce the RC.

1. Branch and / or reopen the tree for further feature submission if appropriate.

Quoted 7 lines
Quoted 5 lines

1. Collect and track any issues reported, determine their severity, prod relevant developers and maintainers to fix the issues.

1. When patches to fix issues are posted, determine if the patches are good to be included.

1. Go back to 1.

To which 1.? There are plenty to choose from. :-D

LOL.

The first "1.". This is a markdown feature I abuse so that I don't have to remember writing the correct numbers.

_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xen.org/xen-devel

#3 lore raw
In reply to Wei Liu

I added Jan because I think we should probably add a section for point releases, which I assume would be a subset of the steps in this document Lars

I will post the notes of the design session also. I am doing the ones first that I moderated and where I took notes in handwriting and/or photos of whiteboard discussions first though, such that I don't miss too much stuff

Lars

Quoted 212 lines · Wei Liu

It is agreed during the summit we should write down such document. Here is my attempt of doing so.

We should probably commit something like this into xen.git so that it gets updated regularly.

Comments are welcome.

-----

% Xen Release Management
% Wei Liu <<[email protected]>>
% Revision 1

# Motivation

Over the years we have had different people from different company signning
up as the Release Manager of Xen. It would be rather wasteful if every new Release Manager has to go over everything and tripped over by the same mistakes again and again.

This file intends to document the process of managing a Xen release. It is mainly written for Release Manager, but other roles (contributors, maintainers and committers) are also encouraged to read this document, so that they can have an idea what to expect from the Release Manager.

# Xen release cycle

The Xen hypervisor project now releases twice a year, at the beginning of June and the beginning of December. The actual release date depends on a lot
of factors.

We can roughly divide one release into two periods. The development period and the freeze period. The former is 4 months long and the latter is about 2
months long.

During development period, contributors submit patches to be reviewed and committed into xen.git.

During freeze period, the tree is closed for new features. Only bug fixes are
accepted. This period can be shorter or longer than 2 months. If it ends up
longer than 2 months, it eats into the next development period.

# The different roles in a Xen release

## Release Manager

A trusted developer in the community that owns the release process. The major
goal of the Release Manager is to make sure a Xen release has high quality and doens't slip too much.

The Release Manager will not see much workload during development period, but
expects to see increasing workload during the freeze period until the final
release. He or she is expected to keep track of issues, arrange RCs, negotiate with relevant stakeholders, balance the need from various parties
and make difficult decisions when necessary.

The Release Manager essentially owns xen-unstable branch during the freeze period. The committers will act on the wishes of the Release Manager during
that time.

## Maintainers

A group of trusted developers who are responsible for certain components in
xen.git. They are expected to respond to patches / questions with regard to
their components in a timely manner, especially during the freeze period.

## Committers

A group of trusted maintainers who can commit to xen.git. During the development window they normally push things as they see fit. During the freeze period they transfer xen-unstable branch ownership and act on the wishes of the Release Manager. That normally means they need to have an Release Ack in order to push a patch.

## Contributors

Contributors are also expected to respond quickly to any issues regarding the
code they submitted during development period. Failing that, the Release Manager might decide to revert the changes, declare feature unsupported or take any action he / she deems appropriate.

## The Security Team

The Security Team operates independently. The visibility might be rather limited due to the sensitive nature of security work. The best action the Release Manager can take is to set aside some time for potential security issues to be fixed.

## The Release Technician

The Release Technician is the person who tags various trees, prepares tarball
etc. He or she acts on the wishes of the Release Manager. Please make sure the communication is as clear as it can be.

## The Community Manager

The Community Manager owns xenproject.org infrastructure. He or she is responsible for updating various web archives, updating wiki pages and coordinating with the PR Personnel.

## The PR Personnel

They are responsible for corrdinating with external reporters to publish Xen
release announcement. The Release Manager should be absolutely sure the release is going out on a particular date before giving them the signal to proceed, because there is a point of no return once they schedule a date with
external reporters.

# What happens during a release

## Development period

Send out monthly update email. The email contains the timeline of the release, the major work items and any other information the Release Manager
sees fit. Please consider adding a recurring event to your calendar.

Occasionally check the status of the xen-unstable branch, make sure it gets
timely pushes to master.

## Freeze period

Before or at very early stage of the freeze period, agree with the Community
Manager a schedule for RC test days.

Once the freeze starts, the ownership of xen-unstable branch automatically transfers to the Release Manager.

Here is a list of things to do for making RCs:

1. Check the status of the tree. Ask the Release Technician to make an RC if the tree is good.

1. Send an email to xen-devel, xen-users and xen-announce to announce the RC.

1. Branch and / or reopen the tree for further feature submission if appropriate.

1. Collect and track any issues reported, determine their severity, prod relevant developers and maintainers to fix the issues.

1. When patches to fix issues are posted, determine if the patches are good to be included.

1. Go back to 1.

It is normally OK in the early RCs that you hand back xen-unstable branch to
committers so that they can commit bug fixes at will. As we approach late RCs, the standard for accepting a patch will get higher and higher. Please communicate clearly when committers can commit at will and when formal Release Ack is needed.

At the same time, work with the Community Manager, PR Personnel and Contributors to gather a list of features for the release. Discuss the support status of new features with stakeholders. Help prepare the press release, write a blog post for the release.

When you think all pending issues are fixed and Xen is ready to be released
from the last RC:

1. Send out commit moratorium emails to committers@.

1. Check all the trees (mini-os, qemu-trad, qemu-xen, seabios, ovmf etc). They have the correct commits and all security patches applied. There will be
tools provided.

1. Ask the Community Manager and Release Technician to double-check all security patches have been applied. If not, apply them, arrange another RC and restart this checklist.

1. Ask the Release Technician to tag the trees and make the tarball. Ask the
Community Manager to update relevant web assets.

1. Give the PR Personnel signal to proceed. Cooridinate with him / her on the
public annoucement.

1. Make the announcement on various mailing list, publish the blog post.

Allow for contigencies. It is not uncommon that some last minute (security or
not) bugs are discovered. To provide a fix takes time, the test of the fix will also take time. Allow for at least 1 week from getting a fix to getting
a push. For security bugs, corrdinate with the Security Team to adjust the dates according to our security policy.

Quoted 28 lines

# Email templates

## RC emails

Quoted 24 lines

Hi all,

Xen X.Y rcZ is tagged. You can check that out from xen.git:

git://xenbits.xen.org/xen.git X.Y.0-rcZ

For your convenience there is also a tarball at:

https://downloads.xenproject.org/release/xen/X.Y.0-rcZ/xen-X.Y.0-rcZ.tar.
gz

And the signature is at:

https://downloads.xenproject.org/release/xen/X.Y.0-rcZ/xen-X.Y.0-rcZ.tar.
gz.sig

Please send bug reports and test reports to [email protected].
When sending bug reports, please CC relevant maintainers and me ([email protected]).

As a reminder, there will be another Xen Test Day.

See instructions on: URL_TO_TEST_INSTRUCTIONS

_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xen.org/xen-devel

#4 lore raw
In reply to Wei Liu

Wei Liu writes ("A document for Xen release management"):

Quoted 2 lines

When you think all pending issues are fixed and Xen is ready to be released from the last RC:

Mostly LGTM. Thanks!

[Items numbered in quoted text so I can refer to them.]

Quoted 10 lines

1. Send out commit moratorium emails to committers@.

2. Check all the trees (mini-os, qemu-trad, qemu-xen, seabios, ovmf etc). They have the correct commits and all security patches applied. There will be tools provided.

3. Ask the Community Manager and Release Technician to double-check all security patches have been applied. If not, apply them, arrange another RC and restart this checklist.

Quoted 5 lines

4. Ask the Release Technician to tag the trees and make the tarball. Ask the Community Manager to update relevant web assets.

5. Give the PR Personnel signal to proceed. Cooridinate with him / her on the public annoucement.

It is OK to make the tarball after giving PR go-ahead. So I suggest

3. Select the release date.

4. Obtain a formal go-ahead from
- the Community Manager
- the Release Technician: ask them to dry-run their checklist and confirm everything is OK.

5. Give PR Personnel go-ahead, and instruct Technician to make release deliverables. (Release deliverables - tags and tarballs - will usually be in place the day before the release.)

Ian.

_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xen.org/xen-devel

#5 lore raw
In reply to Wei Liu
Quoted 7 lines · Wei Liu

It is agreed during the summit we should write down such document. Here is my attempt of doing so.

We should probably commit something like this into xen.git so that it gets updated regularly.

Comments are welcome.

Just to x-ref, see the notes from the meeting at
https://lists.xenproject.org/archives/html/xen-devel/2017-07/threads.html#0
1645
I think I ought to go through the document when the next version is in place and check, whether something has been missed

Lars

Quoted 1 line

_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xen.org/xen-devel

#6 lore raw
In reply to Wei Liu

Hi Wei,

Thank you for writing down the document :).

Quoted 26 lines · Wei Liu

It is agreed during the summit we should write down such document. Here is my attempt of doing so.

We should probably commit something like this into xen.git so that it gets updated regularly.

Comments are welcome.

-----

% Xen Release Management
% Wei Liu <<[email protected]>>
% Revision 1

# Motivation

Over the years we have had different people from different company signning up as the Release Manager of Xen. It would be rather wasteful if every new Release Manager has to go over everything and tripped over by the same mistakes again and again.

This file intends to document the process of managing a Xen release. It is mainly written for Release Manager, but other roles (contributors, maintainers and committers) are also encouraged to read this document, so that they can have an idea what to expect from the Release Manager.

Quoted 5 lines

# Xen release cycle

The Xen hypervisor project now releases twice a year, at the beginning of June and the beginning of December. The actual release date depends on a lot of factors.

Do we have a document detailing the release cycle (e.g last posting date, hard code freeze...)? If not, would it be worth describing the current cut-off scheme here?

Quoted 12 lines

We can roughly divide one release into two periods. The development period and the freeze period. The former is 4 months long and the latter is about 2 months long.

During development period, contributors submit patches to be reviewed and committed into xen.git.

During freeze period, the tree is closed for new features. Only bug fixes are accepted. This period can be shorter or longer than 2 months. If it ends up longer than 2 months, it eats into the next development period.

Quoted 7 lines

# The different roles in a Xen release

## Release Manager

A trusted developer in the community that owns the release process. The major goal of the Release Manager is to make sure a Xen release has high quality and doens't slip too much.

s/doens't/doesn't/

Quoted 47 lines

The Release Manager will not see much workload during development period, but expects to see increasing workload during the freeze period until the final release. He or she is expected to keep track of issues, arrange RCs, negotiate with relevant stakeholders, balance the need from various parties and make difficult decisions when necessary.

The Release Manager essentially owns xen-unstable branch during the freeze period. The committers will act on the wishes of the Release Manager during that time.

## Maintainers

A group of trusted developers who are responsible for certain components in xen.git. They are expected to respond to patches / questions with regard to their components in a timely manner, especially during the freeze period.

## Committers

A group of trusted maintainers who can commit to xen.git. During the development window they normally push things as they see fit. During the freeze period they transfer xen-unstable branch ownership and act on the wishes of the Release Manager. That normally means they need to have an Release Ack in order to push a patch.

## Contributors

Contributors are also expected to respond quickly to any issues regarding the code they submitted during development period. Failing that, the Release Manager might decide to revert the changes, declare feature unsupported or take any action he / she deems appropriate.

## The Security Team

The Security Team operates independently. The visibility might be rather limited due to the sensitive nature of security work. The best action the Release Manager can take is to set aside some time for potential security issues to be fixed.

## The Release Technician

The Release Technician is the person who tags various trees, prepares tarball etc. He or she acts on the wishes of the Release Manager. Please make sure the communication is as clear as it can be.

## The Community Manager

Quoted 7 lines

The Community Manager owns xenproject.org infrastructure. He or she is responsible for updating various web archives, updating wiki pages and coordinating with the PR Personnel.

## The PR Personnel

They are responsible for corrdinating with external reporters to publish Xen

s/corrdinating/coordinating/

Quoted 5 lines

release announcement. The Release Manager should be absolutely sure the release is going out on a particular date before giving them the signal to proceed, because there is a point of no return once they schedule a date with external reporters.

Quoted 7 lines

# What happens during a release

## Development period

Send out monthly update email. The email contains the timeline of the release, the major work items and any other information the Release Manager sees fit. Please consider adding a recurring event to your calendar.

I would also add a paragraph to send remainder a week before at least and "Last posting date" and maybe the "Hard code freeze"?

How about:

"Send out monthly update email. The email contains the timeline of the release, the major work items and any other information the Release Manager sees fit. Reminder should also be sent a week before important cut-off date (e.g last posting date, hard code freeze). Please consider adding a recurring even to your calendar.".

Quoted 46 lines

Occasionally check the status of the xen-unstable branch, make sure it gets timely pushes to master.

## Freeze period

Before or at very early stage of the freeze period, agree with the Community Manager a schedule for RC test days.

Once the freeze starts, the ownership of xen-unstable branch automatically transfers to the Release Manager.

Here is a list of things to do for making RCs:

1. Check the status of the tree. Ask the Release Technician to make an RC if the tree is good.

1. Send an email to xen-devel, xen-users and xen-announce to announce the RC.

1. Branch and / or reopen the tree for further feature submission if appropriate.

1. Collect and track any issues reported, determine their severity, prod relevant developers and maintainers to fix the issues.

1. When patches to fix issues are posted, determine if the patches are good to be included.

1. Go back to 1.

It is normally OK in the early RCs that you hand back xen-unstable branch to committers so that they can commit bug fixes at will. As we approach late RCs, the standard for accepting a patch will get higher and higher. Please communicate clearly when committers can commit at will and when formal Release Ack is needed.

At the same time, work with the Community Manager, PR Personnel and Contributors to gather a list of features for the release. Discuss the support status of new features with stakeholders. Help prepare the press release, write a blog post for the release.

When you think all pending issues are fixed and Xen is ready to be released from the last RC:

1. Send out commit moratorium emails to committers@.

1. Check all the trees (mini-os, qemu-trad, qemu-xen, seabios, ovmf etc). They have the correct commits and all security patches applied. There will be tools provided.

Quoted 8 lines

1. Ask the Community Manager and Release Technician to double-check all security patches have been applied. If not, apply them, arrange another RC and restart this checklist.

1. Ask the Release Technician to tag the trees and make the tarball. Ask the Community Manager to update relevant web assets.

1. Give the PR Personnel signal to proceed. Cooridinate with him / her on the

s/Cooridinate/Coordinate/

Quoted 1 line

public annoucement.

s/annoucement/announcement/

Quoted 4 lines

1. Make the announcement on various mailing list, publish the blog post.

Allow for contigencies. It is not uncommon that some last minute (security or

s/contigencies/contingencies/

Quoted 3 lines

not) bugs are discovered. To provide a fix takes time, the test of the fix will also take time. Allow for at least 1 week from getting a fix to getting a push. For security bugs, corrdinate with the Security Team to adjust the

s/corrdinate/coordinate/

Quoted 26 lines

dates according to our security policy.

# Email templates

## RC emails

Quoted 19 lines

Hi all,

Xen X.Y rcZ is tagged. You can check that out from xen.git:

git://xenbits.xen.org/xen.git X.Y.0-rcZ

For your convenience there is also a tarball at:
https://downloads.xenproject.org/release/xen/X.Y.0-rcZ/xen-X.Y.0-rcZ.tar.gz

And the signature is at:
https://downloads.xenproject.org/release/xen/X.Y.0-rcZ/xen-X.Y.0-rcZ.tar.gz.sig

Please send bug reports and test reports to [email protected]. When sending bug reports, please CC relevant maintainers and me ([email protected]).

As a reminder, there will be another Xen Test Day.

See instructions on: URL_TO_TEST_INSTRUCTIONS

I would consider to add the templates for "Development update" and maybe the script?

## Development update e-mails

This email only tracks big items for xen.git tree. Please reply for items you woulk like to see in $RELEASE_VERSION so that people have an idea what is going on and prioritise accordingly.

You're welcome to provide description and use cases of the feature you're working on.

= Timeline =

We now adopt a fixed cut-off date scheme. We will release twice a year. The upcoming $RELEASE_VERSION timeline are as followed:

* Last posting date: $RELEASE_CUTOFF
* Hard code freeze: $RELEASE_FREEZE
* RC1: TBD
* Release: $RELEASE_DATE

Note that we don't have freeze exception scheme anymore. All patches that wish to go into $RELEASE_VERSION must be posted no later than the last posting date. All patches posted after that date will be automatically queued into next release.

RCs will be arranged immediately after freeze.

We recently introduced a jira instance to track all the tasks (not only big) for the project. See: https://xenproject.atlassian.net/projects/XEN/issues.

Most of the tasks tracked by this e-mail also have a corresponding jira task referred by XEN-N.

I have started to include the version number of series associated to each feature. Can each owner send an update on the version number if the series was posted upstream?

= Projects =

Cheers,

Signature · 6 lines
Julien Grall

_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xen.org/xen-devel
author
#7 lore raw
Quoted 33 lines · Julien Grall

Hi Wei,

Thank you for writing down the document :).

Quoted 28 lines · Wei Liu

It is agreed during the summit we should write down such document. Here is my attempt of doing so.

We should probably commit something like this into xen.git so that it gets updated regularly.

Comments are welcome.

-----

% Xen Release Management
% Wei Liu <<[email protected]>>
% Revision 1

# Motivation

Over the years we have had different people from different company signning up as the Release Manager of Xen. It would be rather wasteful if every new Release Manager has to go over everything and tripped over by the same mistakes again and again.

This file intends to document the process of managing a Xen release. It is mainly written for Release Manager, but other roles (contributors, maintainers and committers) are also encouraged to read this document, so that they can have an idea what to expect from the Release Manager.

# Xen release cycle

Quoted 7 lines
Quoted 3 lines

The Xen hypervisor project now releases twice a year, at the beginning of June and the beginning of December. The actual release date depends on a lot of factors.

Do we have a document detailing the release cycle (e.g last posting date, hard code freeze...)? If not, would it be worth describing the current cut-off scheme here?

Sure.

[...]

Quoted 15 lines
Quoted 11 lines

release is going out on a particular date before giving them the signal to proceed, because there is a point of no return once they schedule a date with external reporters.

# What happens during a release

## Development period

Send out monthly update email. The email contains the timeline of the release, the major work items and any other information the Release Manager sees fit. Please consider adding a recurring event to your calendar.

I would also add a paragraph to send remainder a week before at least and "Last posting date" and maybe the "Hard code freeze"?

Quoted 8 lines

How about:

"Send out monthly update email. The email contains the timeline of the release, the major work items and any other information the Release Manager sees fit. Reminder should also be sent a week before important cut-off date (e.g last posting date, hard code freeze). Please consider adding a recurring even to your calendar.".

SGTM.

[...]

Quoted 20 lines
Quoted 20 lines

# Email templates

## RC emails

Quoted 16 lines

Hi all,

Xen X.Y rcZ is tagged. You can check that out from xen.git:

git://xenbits.xen.org/xen.git X.Y.0-rcZ

For your convenience there is also a tarball at:
https://downloads.xenproject.org/release/xen/X.Y.0-rcZ/xen-X.Y.0-rcZ.tar.gz

And the signature is at:
https://downloads.xenproject.org/release/xen/X.Y.0-rcZ/xen-X.Y.0-rcZ.tar.gz.sig

Please send bug reports and test reports to [email protected]. When sending bug reports, please CC relevant maintainers and me ([email protected]).

Quoted 7 lines
Quoted 3 lines
Quoted 3 lines

As a reminder, there will be another Xen Test Day.

See instructions on: URL_TO_TEST_INSTRUCTIONS

I would consider to add the templates for "Development update" and maybe the script?

Yeah, just paste in a stripped down version of the script you use here.

_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xen.org/xen-devel

#8 lore raw
In reply to Wei Liu

Hi all,

I went over this with a few of the actions from https://lists.xenproject.org/archives/html/xen-devel/2017-07/threads.html#01645 <https://lists.xenproject.org/archives/html/xen-devel/2017-07/threads.html#01645>

Lars/Wei/Julien
A1 ACTION to write "standard e-mail templates for common stuff", rather than re-doing these every single time Ian release manager file

A2 ACTION : Clean up release technician checklist after we have the how to be
* Add hand-over of tasks for Release Manager responsibility to the "how to be release manager file"

A3 ACTION: Additional stuff to add to the templates/RM guide
A3.1: Add clear reminders in particular at the beginning of a release into e-mail templates: such as put dates X,Y, Z in your calendar add to checklist and templates A3.2: Communicate better when tree is open again
A3.3: Release manager can say "not releasing now" because of too many bugs, "until someone fixes these". "no more patches until XYZ"

Looking through it, I am not sure whether A3.2 and 3.3 are covered.

Lars

Quoted 150 lines · Wei Liu

It is agreed during the summit we should write down such document. Here is my attempt of doing so.

We should probably commit something like this into xen.git so that it gets updated regularly.

Comments are welcome.

-----

% Xen Release Management
% Wei Liu <<[email protected]>>
% Revision 1

# Motivation

Over the years we have had different people from different company signning up as the Release Manager of Xen. It would be rather wasteful if every new Release Manager has to go over everything and tripped over by the same mistakes again and again.

This file intends to document the process of managing a Xen release. It is mainly written for Release Manager, but other roles (contributors, maintainers and committers) are also encouraged to read this document, so that they can have an idea what to expect from the Release Manager.

# Xen release cycle

The Xen hypervisor project now releases twice a year, at the beginning of June and the beginning of December. The actual release date depends on a lot of factors.

We can roughly divide one release into two periods. The development period and the freeze period. The former is 4 months long and the latter is about 2 months long.

During development period, contributors submit patches to be reviewed and committed into xen.git.

During freeze period, the tree is closed for new features. Only bug fixes are accepted. This period can be shorter or longer than 2 months. If it ends up longer than 2 months, it eats into the next development period.

# The different roles in a Xen release

## Release Manager

A trusted developer in the community that owns the release process. The major goal of the Release Manager is to make sure a Xen release has high quality and doens't slip too much.

The Release Manager will not see much workload during development period, but expects to see increasing workload during the freeze period until the final release. He or she is expected to keep track of issues, arrange RCs, negotiate with relevant stakeholders, balance the need from various parties and make difficult decisions when necessary.

The Release Manager essentially owns xen-unstable branch during the freeze period. The committers will act on the wishes of the Release Manager during that time.

## Maintainers

A group of trusted developers who are responsible for certain components in xen.git. They are expected to respond to patches / questions with regard to their components in a timely manner, especially during the freeze period.

## Committers

A group of trusted maintainers who can commit to xen.git. During the development window they normally push things as they see fit. During the freeze period they transfer xen-unstable branch ownership and act on the wishes of the Release Manager. That normally means they need to have an Release Ack in order to push a patch.

## Contributors

Contributors are also expected to respond quickly to any issues regarding the code they submitted during development period. Failing that, the Release Manager might decide to revert the changes, declare feature unsupported or take any action he / she deems appropriate.

## The Security Team

The Security Team operates independently. The visibility might be rather limited due to the sensitive nature of security work. The best action the Release Manager can take is to set aside some time for potential security issues to be fixed.

## The Release Technician

The Release Technician is the person who tags various trees, prepares tarball etc. He or she acts on the wishes of the Release Manager. Please make sure the communication is as clear as it can be.

## The Community Manager

The Community Manager owns xenproject.org infrastructure. He or she is responsible for updating various web archives, updating wiki pages and coordinating with the PR Personnel.

## The PR Personnel

They are responsible for corrdinating with external reporters to publish Xen release announcement. The Release Manager should be absolutely sure the release is going out on a particular date before giving them the signal to proceed, because there is a point of no return once they schedule a date with external reporters.

# What happens during a release

## Development period

Send out monthly update email. The email contains the timeline of the release, the major work items and any other information the Release Manager sees fit. Please consider adding a recurring event to your calendar.

Occasionally check the status of the xen-unstable branch, make sure it gets timely pushes to master.

## Freeze period

Before or at very early stage of the freeze period, agree with the Community Manager a schedule for RC test days.

Once the freeze starts, the ownership of xen-unstable branch automatically transfers to the Release Manager.

Here is a list of things to do for making RCs:

1. Check the status of the tree. Ask the Release Technician to make an RC if the tree is good.

1. Send an email to xen-devel, xen-users and xen-announce to announce the RC.

1. Branch and / or reopen the tree for further feature submission if appropriate.

1. Collect and track any issues reported, determine their severity, prod relevant developers and maintainers to fix the issues.

1. When patches to fix issues are posted, determine if the patches are good to be included.

1. Go back to 1.

It is normally OK in the early RCs that you hand back xen-unstable branch to committers so that they can commit bug fixes at will. As we approach late RCs, the standard for accepting a patch will get higher and higher. Please communicate clearly when committers can commit at will and when formal Release Ack is needed.

Quoted 4 lines

At the same time, work with the Community Manager, PR Personnel and Contributors to gather a list of features for the release. Discuss the support status of new features with stakeholders. Help prepare the press release, write a blog post for the release.

Does it make sense to move this into a separate section, or have a separate section which list the key steps? If so, I am happy to pull this together. Primarily I tend to drive the PR angle with Zibby and would be happy to create a checklist. The Release Manager's role here is one of providing input, but can (if desired) be more high profile (e.g. quotes in releases).

Quoted 6 lines

When you think all pending issues are fixed and Xen is ready to be released from the last RC:

1. Send out commit moratorium emails to committers@.

Quoted 7 lines

1. Check all the trees (mini-os, qemu-trad, qemu-xen, seabios, ovmf etc). They have the correct commits and all security patches applied. There will be tools provided.

1. Ask the Community Manager and Release Technician to double-check all security patches have been applied. If not, apply them, arrange another RC and restart this checklist.

I think double checking is good. If http://xenbits.xenproject.org/gitweb/?p=people/larsk/xen-release-scripts.git <http://xenbits.xenproject.org/gitweb/?p=people/larsk/xen-release-scripts.git> are deemed to be fit for purpose, we should probably refer to these

Quoted 2 lines

1. Ask the Release Technician to tag the trees and make the tarball. Ask the Community Manager to update relevant web assets.

Add:

1. Check with relevant stake-holders (typically community manager) whether wiki documentation and PR is in good shape (for an example see https://wiki.xenproject.org/wiki/Category:Xen_4.9 <https://wiki.xenproject.org/wiki/Category:Xen_4.9>)

Quoted 3 lines

1. Give the PR Personnel signal to proceed. Cooridinate with him / her on the public annoucement.

Typically we will need a bit of lead-time here to ensure that everything is in place

Quoted 9 lines

1. Make the announcement on various mailing list, publish the blog post.

Allow for contigencies. It is not uncommon that some last minute (security or not) bugs are discovered. To provide a fix takes time, the test of the fix will also take time. Allow for at least 1 week from getting a fix to getting a push. For security bugs, corrdinate with the Security Team to adjust the dates according to our security policy.

There should probably be a section along the lines of (for A2)

## Hand over of Release Manager Responsibility

Probably this is an area where Wei, George, Konrad and Julien have experience.

This should include a list of systems a Release Manager should be signed up to, such as blog account, xen-announce, ...

Quoted 23 lines

# Email templates

## RC emails

Quoted 19 lines

Hi all,

Xen X.Y rcZ is tagged. You can check that out from xen.git:

git://xenbits.xen.org/xen.git X.Y.0-rcZ

For your convenience there is also a tarball at:
https://downloads.xenproject.org/release/xen/X.Y.0-rcZ/xen-X.Y.0-rcZ.tar.gz

And the signature is at:
https://downloads.xenproject.org/release/xen/X.Y.0-rcZ/xen-X.Y.0-rcZ.tar.gz.sig

Please send bug reports and test reports to [email protected]. When sending bug reports, please CC relevant maintainers and me ([email protected]).

As a reminder, there will be another Xen Test Day.

See instructions on: URL_TO_TEST_INSTRUCTIONS

We should probably have mail templates for the specific stages of the process, which can then include reminders to add calendar entries (see A3.1)

_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xen.org/xen-devel

author
#9 lore raw
Quoted 8 lines · Lars Kurth

Hi all,

I went over this with a few of the actions from https://lists.xenproject.org/archives/html/xen-devel/2017-07/threads.html#01645 <https://lists.xenproject.org/archives/html/xen-devel/2017-07/threads.html#01645>

Lars/Wei/Julien
A1 ACTION to write "standard e-mail templates for common stuff", rather than re-doing these every single time Ian release manager file

Quoted 7 lines

A2 ACTION : Clean up release technician checklist after we have the how to be
* Add hand-over of tasks for Release Manager responsibility to the "how to be release manager file"

A3 ACTION: Additional stuff to add to the templates/RM guide
A3.1: Add clear reminders in particular at the beginning of a release into e-mail templates: such as put dates X,Y, Z in your calendar add to checklist and templates A3.2: Communicate better when tree is open again
A3.3: Release manager can say "not releasing now" because of too many bugs, "until someone fixes these". "no more patches until XYZ"

Hmm... let's make these more obvious then.

Quoted 16 lines
Quoted 10 lines

1. Go back to 1.

It is normally OK in the early RCs that you hand back xen-unstable branch to committers so that they can commit bug fixes at will. As we approach late RCs, the standard for accepting a patch will get higher and higher. Please communicate clearly when committers can commit at will and when formal Release Ack is needed.

Quoted 4 lines

At the same time, work with the Community Manager, PR Personnel and Contributors to gather a list of features for the release. Discuss the support status of new features with stakeholders. Help prepare the press release, write a blog post for the release.

Quoted 7 lines

Does it make sense to move this into a separate section, or have a separate section which list the key steps? If so, I am happy to pull this together. Primarily I tend to drive the PR angle with Zibby and would be happy to create a checklist. The Release Manager's role here is one of providing input, but can (if desired) be more high profile (e.g. quotes in releases).

Yes, I think that would be good.

Quoted 29 lines
Quoted 6 lines

When you think all pending issues are fixed and Xen is ready to be released from the last RC:

1. Send out commit moratorium emails to committers@.

Quoted 7 lines

1. Check all the trees (mini-os, qemu-trad, qemu-xen, seabios, ovmf etc). They have the correct commits and all security patches applied. There will be tools provided.

1. Ask the Community Manager and Release Technician to double-check all security patches have been applied. If not, apply them, arrange another RC and restart this checklist.

I think double checking is good. If http://xenbits.xenproject.org/gitweb/?p=people/larsk/xen-release-scripts.git <http://xenbits.xenproject.org/gitweb/?p=people/larsk/xen-release-scripts.git> are deemed to be fit for purpose, we should probably refer to these

Quoted 2 lines

1. Ask the Release Technician to tag the trees and make the tarball. Ask the Community Manager to update relevant web assets.

Add:

1. Check with relevant stake-holders (typically community manager) whether wiki documentation and PR is in good shape (for an example see
https://wiki.xenproject.org/wiki/Category:Xen_4.9
<https://wiki.xenproject.org/wiki/Category:Xen_4.9>)

Quoted 1 line
Quoted 4 lines
Quoted 2 lines

1. Give the PR Personnel signal to proceed. Cooridinate with him / her on the public annoucement.

Typically we will need a bit of lead-time here to ensure that everything is in place

How much time would be considered typical?

I'm not sure the steps involved to get PR done. Maybe you can clarify in the section you volunteered to write. And then, we can define what RM needs to do based on that.

Quoted 12 lines
Quoted 11 lines

1. Make the announcement on various mailing list, publish the blog post.

Allow for contigencies. It is not uncommon that some last minute (security or not) bugs are discovered. To provide a fix takes time, the test of the fix will also take time. Allow for at least 1 week from getting a fix to getting a push. For security bugs, corrdinate with the Security Team to adjust the dates according to our security policy.

Quoted 8 lines

There should probably be a section along the lines of (for A2)

## Hand over of Release Manager Responsibility

Probably this is an area where Wei, George, Konrad and Julien have experience.

This should include a list of systems a Release Manager should be signed up to, such as blog account, xen-announce, ...

The most valuable thing to hand over is the script to generate emails, which we already planned to include in this file.

I think mentioning various creation is good.

Quoted 20 lines
Quoted 20 lines

# Email templates

## RC emails

Quoted 16 lines

Hi all,

Xen X.Y rcZ is tagged. You can check that out from xen.git:

git://xenbits.xen.org/xen.git X.Y.0-rcZ

For your convenience there is also a tarball at:
https://downloads.xenproject.org/release/xen/X.Y.0-rcZ/xen-X.Y.0-rcZ.tar.gz

And the signature is at:
https://downloads.xenproject.org/release/xen/X.Y.0-rcZ/xen-X.Y.0-rcZ.tar.gz.sig

Please send bug reports and test reports to [email protected]. When sending bug reports, please CC relevant maintainers and me ([email protected]).

Quoted 7 lines
Quoted 3 lines
Quoted 3 lines

As a reminder, there will be another Xen Test Day.

See instructions on: URL_TO_TEST_INSTRUCTIONS

We should probably have mail templates for the specific stages of the process, which can then include reminders to add calendar entries (see A3.1)

OK.

Quoted 1 line