Hi,

The integration deadline is passed by one week, and the first release candidate is still far from being ready.
This time it is really, really late.
We will try to do this RC1 on the 20th of April, but no guarantee.

Then we may have a lot of new drivers or features to integrate in the next release candidate. So we need to plan two weeks of work before releasing the RC2 around the 4th of May, which was the date initially targeted for the release 18.05.

Usually we need two more weeks of bug fixing in RC3 and RC4, and few more days of validation before the release.
It means the release will happen on the 23rd of May in the "best case".

During this time, we need everybody's help to finish the reviews.

If you are not involved in reviews or last minute adjustments, you can start working on new stuff for 18.08, because the preparation period before the proposal deadline will be tight. We can think about delaying the proposal deadline for 18.08 by one week (June, 8th). We should also accept that the 18.08 release might be smaller than usual.

Thanks for understanding and helps

#1 lore raw

Hi,

Please find an update of the release status, inline below.

13/04/2018 00:01, Thomas Monjalon:

Quoted 4 lines

The integration deadline is passed by one week, and the first release candidate is still far from being ready.
This time it is really, really late.
We will try to do this RC1 on the 20th of April, but no guarantee.

.. no guarantee, indeed.
There are 742 patches in master, 56 in next-net, 68 in next-crypto, and a lot more not yet merged.
List of remaining significant patches for RC1:

missing in next-net
- runtime queue setup
- new VXLAN and MPLS tunnels
- generic IP/UDP tunnel offloads
- tunnel encap/decap
- flow API related fixes
- flow API overhaul for switch offloads
- rte_flow extension for vSwitch
- switching devices representation
missing in master:
- secondary vdev
- replace calls to rte_panic
- control threads
- symbolic log levels
- devargs cleanup
- device querying
- mbuf external
- mempool bucket driver

Quoted 4 lines

Then we may have a lot of new drivers or features to integrate in the next release candidate. So we need to plan two weeks of work before releasing the RC2 around the 4th of May, which was the date initially targeted for the release 18.05.

List of major patches for RC2:
- compressdev
- DPAA2 QDMA raw driver
- DPAA2 Command Interface raw driver
- Hyper-V bus and NetVSC PMD
- Intel FPGA
- BPF

Quoted 5 lines

Usually we need two more weeks of bug fixing in RC3 and RC4, and few more days of validation before the release.
It means the release will happen on the 23rd of May in the "best case".

During this time, we need everybody's help to finish the reviews.