Hi Keir,

I vaguely recall a statement of yours a couple of weeks back to start the RC-phase for 4.0.2 almost right away. As this didn't happen, I wonder what the current plans are.

Thanks, Jan

#1 lore raw
Quoted 5 lines · Jan Beulich

Hi Keir,

I vaguely recall a statement of yours a couple of weeks back to start the RC-phase for 4.0.2 almost right away. As this didn't happen, I wonder what the current plans are.

The hypervisor bits are ready, just need sign off on tools, qemu, and testing. And a QEMU_TAG. That's all mostly Ian Jackson.

-- Keir

Quoted 2 lines

Thanks, Jan

#2 lore raw

Keir Fraser writes ("[Xen-devel] Re: 4.0.2 plans?"):

Quoted 8 lines · Jan Beulich
Quoted 4 lines

I vaguely recall a statement of yours a couple of weeks back to start the RC-phase for 4.0.2 almost right away. As this didn't happen, I wonder what the current plans are.

The hypervisor bits are ready, just need sign off on tools, qemu, and testing. And a QEMU_TAG. That's all mostly Ian Jackson.

We're happy with the state of the tools; I've just pushed one last change to qemu. When we get a test pass and auto-push, which ought not to take too long, we can tag 4.0.2 rc1.

Ian.