can we shorten/elongate (doesnt matter to me) the next release process ? the original time frame was picked so as to not overlap with the linux kernel, but the current merge window did exactly that :(.
-mike
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: application/pgp-signature
Size: 836 bytes
Desc: This is a digitally signed message part.
Url : http://lists.denx.de/pipermail/u-boot/attachments/20090402/c75d3dcc/attachment.pgp

#1 lore raw

Dear Mike,

Quoted 4 lines · In message <[email protected]> you wrote:

can we shorten/elongate (doesnt matter to me) the next release process ? the original time frame was picked so as to not overlap with the linux kernel, but the current merge window did exactly that :(.

Yes, I'm aware of this, but at least it's not our fault. We've been releasing mostly on schedule, it was the Linux kernel releases that shifted and shifted...

Shorten is IMHO not an option, but we can delay it.

Please suggest where and when? Make this merge window longer by one week, and this testing phase longer by two weeks?

Best regards,

Wolfgang Denk

Signature · 6 lines
DENX Software Engineering GmbH,     MD: Wolfgang Denk & Detlev Zundel
HRB 165235 Munich, Office: Kirchenstr.5, D-82194 Groebenzell, Germany
Phone: (+49)-8142-66989-10 Fax: (+49)-8142-66989-80 Email: wd at denx.de
We do not colonize. We conquer. We rule. There is no  other  way  for
us.
	-- Rojan, "By Any Other Name", stardate 4657.5
#2 lore raw
Quoted 8 lines · Wolfgang Denk

Dear Mike,

Quoted 4 lines · In message <[email protected]> you wrote:

can we shorten/elongate (doesnt matter to me) the next release process ? the original time frame was picked so as to not overlap with the linux kernel, but the current merge window did exactly that :(.

Quoted 8 lines

Yes, I'm aware of this, but at least it's not our fault. We've been releasing mostly on schedule, it was the Linux kernel releases that shifted and shifted...

Shorten is IMHO not an option, but we can delay it.

Please suggest where and when? Make this merge window longer by one week, and this testing phase longer by two weeks?

why not create a release to integrate the Kconfig?

Best Regards,
J.

#3 lore raw

Dear Jean-Christophe PLAGNIOL-VILLARD,

Quoted 4 lines · In message <[email protected]> you wrote:
Quoted 3 lines

Please suggest where and when? Make this merge window longer by one week, and this testing phase longer by two weeks?

why not create a release to integrate the Kconfig?

You would still have to pla for that release, and schedule it.

Feel free to submit the Kconfig stuff for 2009.07. Or now, the merge window is stil open :-)

Best regards,

Wolfgang Denk

Signature · 5 lines
DENX Software Engineering GmbH,     MD: Wolfgang Denk & Detlev Zundel
HRB 165235 Munich, Office: Kirchenstr.5, D-82194 Groebenzell, Germany
Phone: (+49)-8142-66989-10 Fax: (+49)-8142-66989-80 Email: wd at denx.de
As long as we're going to reinvent the wheel again, we might as  well
try making it round this time.                        - Mike Dennison
#4 lore raw
Quoted 4 lines · Wolfgang Denk

Dear Jean-Christophe PLAGNIOL-VILLARD,

Quoted 1 line · In message <[email protected]> you wrote:
Quoted 8 lines
Quoted 3 lines
Quoted 2 lines

Please suggest where and when? Make this merge window longer by one week, and this testing phase longer by two weeks?

why not create a release to integrate the Kconfig?

You would still have to pla for that release, and schedule it.

Feel free to submit the Kconfig stuff for 2009.07. Or now, the merge window is stil open :-)

I've not finished but near

the only thing is that we will need time to write all the Kconfig

so these 3 weeks could be you use for this purpose specialy if no drivers will added every day

Best Regards,
J.

#5 lore raw
In reply to Wolfgang Denk
Quoted 5 lines · On Thursday 02 April 2009 07:40:09 Wolfgang Denk wrote:
Quoted 3 lines · In message Mike

can we shorten/elongate (doesnt matter to me) the next release process ? the original time frame was picked so as to not overlap with the linux kernel, but the current merge window did exactly that :(.

Quoted 8 lines

Yes, I'm aware of this, but at least it's not our fault. We've been releasing mostly on schedule, it was the Linux kernel releases that shifted and shifted...

Shorten is IMHO not an option, but we can delay it.

Please suggest where and when? Make this merge window longer by one week, and this testing phase longer by two weeks?

that sounds reasonable to me ... maybe leave the exact release time in May open so that if the kernel releases sooner, we can push out, or if it releases later, we can push up.
-mike
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: application/pgp-signature
Size: 836 bytes
Desc: This is a digitally signed message part.
Url : http://lists.denx.de/pipermail/u-boot/attachments/20090402/54f7b206/attachment.pgp

#6 lore raw
Quoted 14 lines · Mike Frysinger
Quoted 13 lines · On Thursday 02 April 2009 07:40:09 Wolfgang Denk wrote:
Quoted 5 lines · In message Mike

can we shorten/elongate (doesnt matter to me) the next release process ?
the original time frame was picked so as to not overlap with the linux
kernel, but the current merge window did exactly that :(.

Yes, I'm aware of this, but at least it's not our fault. We've been releasing mostly on schedule, it was the Linux kernel releases that shifted and shifted...

Shorten is IMHO not an option, but we can delay it.

Quoted 8 lines
Quoted 2 lines

Please suggest where and when? Make this merge window longer by one week, and this testing phase longer by two weeks?

that sounds reasonable to me ... maybe leave the exact release time in May
open so that if the kernel releases sooner, we can push out, or if it releases
later, we can push up.

What's the concern w/overlap or conflict with the kernel release? I doubt whatever we pick will ever be insync w/the kernel.

- k

#7 lore raw
Quoted 14 lines · On Thursday 02 April 2009 09:27:55 Kumar Gala wrote:
Quoted 13 lines · Mike Frysinger
Quoted 12 lines · On Thursday 02 April 2009 07:40:09 Wolfgang Denk wrote:
Quoted 4 lines · In message Mike

can we shorten/elongate (doesnt matter to me) the next release process ?
the original time frame was picked so as to not overlap with the linux kernel, but the current merge window did exactly that :(.

Yes, I'm aware of this, but at least it's not our fault. We've been releasing mostly on schedule, it was the Linux kernel releases that shifted and shifted...

Shorten is IMHO not an option, but we can delay it.

Quoted 8 lines
Quoted 6 lines
Quoted 2 lines

Please suggest where and when? Make this merge window longer by one week, and this testing phase longer by two weeks?

that sounds reasonable to me ... maybe leave the exact release time in May open so that if the kernel releases sooner, we can push out, or if it releases later, we can push up.

What's the concern w/overlap or conflict with the kernel release?

it's pretty common for people who work on u-boot to also work on the kernel. trying to balance merge windows of two major projects simultaneously is unnecessarily strenuous.

Quoted 1 line

I doubt whatever we pick will ever be insync w/the kernel.

the idea is to be out of sync ;). no, things wont always line up perfectly, but that doesnt mean we cant adjust when the kernel does change.
-mike
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: application/pgp-signature
Size: 836 bytes
Desc: This is a digitally signed message part.
Url : http://lists.denx.de/pipermail/u-boot/attachments/20090402/f9d4e0db/attachment.pgp

#8 lore raw
In reply to Mike Frysinger

Hello everybody

Quoted 4 lines · in message <[email protected]> Mike Frysinger wrote:

can we shorten/elongate (doesnt matter to me) the next release process ? the original time frame was picked so as to not overlap with the linux kernel, but the current merge window did exactly that :(.

This being a correct and reasonable request, I decided to extend the stabilzation phase for the next release by 3 weeks. i. e. the release schedule (see also http://www.denx.de/wiki/U-Boot/ReleaseCycle) now looks like this:

- The next version will be called v2009.06

- The merge window for v2009.06 closes in 2 hours from now. So better hurry up if you still want to get something into this release ;-)

- The release of v2009.06 is scheduled for Sunday, June 14, 2009.

Best regards,

Wolfgang Denk

Signature · 4 lines
DENX Software Engineering GmbH,     MD: Wolfgang Denk & Detlev Zundel
HRB 165235 Munich, Office: Kirchenstr.5, D-82194 Groebenzell, Germany
Phone: (+49)-8142-66989-10 Fax: (+49)-8142-66989-80 Email: wd at denx.de
There's no future in time travel.