Exception for the release schedule?
Peter,
According to our usual release schedule, 2012.11-rc1 should be released at the end of October, and the final 2012.11 at the end November.
Do you think it would be possible to make an exception, and delay 2012.11-rc1 by one week? This would allow 2012.11-rc1 to be released *after* the Buildroot Developers Meeting (November 3-4) in Barcelona. This would be nice since I expect within the two days of this meeting that we will review and ack quite a bit of pending material, which would be good to have in 2012.11.
What do you think of this?
Best regards,
Thomas
Signature · 4 lines
Thomas Petazzoni, Free Electrons Kernel, drivers, real-time and embedded Linux development, consulting, training and support. http://free-electrons.com
Quoted 1 line
Quoted 1 line
Quoted 1 line
Quoted 1 line
Quoted 1 line
"Thomas" == Thomas Petazzoni <[email protected]> writes:
Thomas> Peter,
Thomas> According to our usual release schedule, 2012.11-rc1 should be released Thomas> at the end of October, and the final 2012.11 at the end November.
Thomas> Do you think it would be possible to make an exception, and Thomas> delay 2012.11-rc1 by one week? This would allow 2012.11-rc1 to Thomas> be released *after* the Buildroot Developers Meeting (November Thomas> 3-4) in Barcelona. This would be nice since I expect within Thomas> the two days of this meeting that we will review and ack quite Thomas> a bit of pending material, which would be good to have in Thomas> 2012.11.
Thomas> What do you think of this?
Yes, I agree 100%. I did similar with 2012.02 (Fosdem).
Signature · 1 line
Bye, Peter Korsgaard
Dear Peter Korsgaard,
Quoted 1 line · Peter Korsgaard
Yes, I agree 100%. I did similar with 2012.02 (Fosdem).
Excellent, thanks!
Thomas
Signature · 4 lines
Thomas Petazzoni, Free Electrons Kernel, drivers, real-time and embedded Linux development, consulting, training and support. http://free-electrons.com
Quoted 5 lines · Thomas Petazzoni
Peter,
According to our usual release schedule, 2012.11-rc1 should be released at the end of October, and the final 2012.11 at the end November.
Quoted 8 lines
Do you think it would be possible to make an exception, and delay 2012.11-rc1 by one week? This would allow 2012.11-rc1 to be released *after* the Buildroot Developers Meeting (November 3-4) in Barcelona. This would be nice since I expect within the two days of this meeting that we will review and ack quite a bit of pending material, which would be good to have in 2012.11.
What do you think of this?
Excellent plan!
Regards,
Arnout
Signature · 6 lines
Arnout Vandecappelle arnout at mind be Senior Embedded Software Architect +32-16-286540 Essensium/Mind http://www.mind.be G.Geenslaan 9, 3001 Leuven, Belgium BE 872 984 063 RPR Leuven LinkedIn profile: http://www.linkedin.com/in/arnoutvandecappelle GPG fingerprint: 7CB5 E4CC 6C2E EFD4 6E3D A754 F963 ECAB 2450 2F1F