Xen 4.12 release planning
Its time to plan the Xen 4.12 release dates.
There have been concerns with the schedule of 6 months between releases, as this scheme is leading to too many supported versions of Xen at a time. The needed resources to backport bug fixes and security fixes as well as doing the tests for all those releases are a limiting factor to push out the current main release as well as point releases on time.
After some discussions at the Xen developer summit, on xen-devel and between the committers a slightly longer release cycle of 8 or 9 months was suggested.
With 18 months of full support and 36 months of security support the number of concurrent supported releases will be the same with either 8 or 9 months release cycles, so I have chosen an 8 month cycle for now. Having only 3 possible times in the year for a release will make it easier to avoid major holiday seasons.
In case there is no objection I'm planning Xen 4.12 with:
* Last posting date: December 14th, 2018
* Hard code freeze: January 11th, 2019
* Release: March 7th, 2019
Release of Xen 4.13 would then be early November 2019, 4.14 at early July 2020.
Juergen
_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xenproject.org/mailman/listinfo/xen-devel
Hi Juergen,
Quoted 19 lines · Juergen Gross
Its time to plan the Xen 4.12 release dates.
There have been concerns with the schedule of 6 months between releases, as this scheme is leading to too many supported versions of Xen at a time. The needed resources to backport bug fixes and security fixes as well as doing the tests for all those releases are a limiting factor to push out the current main release as well as point releases on time.
After some discussions at the Xen developer summit, on xen-devel and between the committers a slightly longer release cycle of 8 or 9 months was suggested.
With 18 months of full support and 36 months of security support the number of concurrent supported releases will be the same with either 8 or 9 months release cycles, so I have chosen an 8 month cycle for now. Having only 3 possible times in the year for a release will make it easier to avoid major holiday seasons. >
In case there is no objection I'm planning Xen 4.12 with:
Quoted 2 lines
* Last posting date: December 14th, 2018
* Hard code freeze: January 11th, 2019
In general, you would expect western people to slow down during Christmas period and have to deal with a pile of e-mail just after New Year. So I think, this is not very convenient period for a code freeze.
I usually take more holidays around Christmas and New Year. For this year, I will be on holidays from 21st December until the 13th January. This basically means my cut off for Arm patches will be 21st December or potentially few days before to avoid having the likely last minute rush.
Cheers,
Signature · 6 lines
Julien Grall _______________________________________________ Xen-devel mailing list [email protected] https://lists.xenproject.org/mailman/listinfo/xen-devel
Quoted 29 lines · Julien Grall
Hi Juergen,
Quoted 19 lines · Juergen Gross
Its time to plan the Xen 4.12 release dates.
There have been concerns with the schedule of 6 months between releases, as this scheme is leading to too many supported versions of Xen at a time. The needed resources to backport bug fixes and security fixes as well as doing the tests for all those releases are a limiting factor to push out the current main release as well as point releases on time.
After some discussions at the Xen developer summit, on xen-devel and between the committers a slightly longer release cycle of 8 or 9 months was suggested.
With 18 months of full support and 36 months of security support the number of concurrent supported releases will be the same with either 8 or 9 months release cycles, so I have chosen an 8 month cycle for now. Having only 3 possible times in the year for a release will make it easier to avoid major holiday seasons. >
In case there is no objection I'm planning Xen 4.12 with:Quoted 2 lines
* Last posting date: December 14th, 2018
* Hard code freeze: January 11th, 2019In general, you would expect western people to slow down during Christmas period and have to deal with a pile of e-mail just after New Year. So I think, this is not very convenient period for a code freeze.
Quoted 5 lines
I usually take more holidays around Christmas and New Year. For this year, I will be on holidays from 21st December until the 13th January. This basically means my cut off for Arm patches will be 21st December or potentially few days before to avoid having the likely last minute rush.
Given that we have decided to switch to a difference cadence, it would be prudent to work out when the best alignment of an 8-month cadence would be, rather than having it 8 months from now. If that means a one-off shorter or longer cycle for 4.12 then so be it.
~Andrew
_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xenproject.org/mailman/listinfo/xen-devel
Quoted 36 lines · Andrew Cooper
Quoted 29 lines · Julien Grall
Hi Juergen,
Quoted 19 lines · Juergen Gross
Its time to plan the Xen 4.12 release dates.
There have been concerns with the schedule of 6 months between releases, as this scheme is leading to too many supported versions of Xen at a time. The needed resources to backport bug fixes and security fixes as well as doing the tests for all those releases are a limiting factor to push out the current main release as well as point releases on time.
After some discussions at the Xen developer summit, on xen-devel and between the committers a slightly longer release cycle of 8 or 9 months was suggested.
With 18 months of full support and 36 months of security support the number of concurrent supported releases will be the same with either 8 or 9 months release cycles, so I have chosen an 8 month cycle for now. Having only 3 possible times in the year for a release will make it easier to avoid major holiday seasons. >
In case there is no objection I'm planning Xen 4.12 with:Quoted 2 lines
* Last posting date: December 14th, 2018
* Hard code freeze: January 11th, 2019In general, you would expect western people to slow down during Christmas period and have to deal with a pile of e-mail just after New Year. So I think, this is not very convenient period for a code freeze.
Quoted 5 lines
I usually take more holidays around Christmas and New Year. For this year, I will be on holidays from 21st December until the 13th January. This basically means my cut off for Arm patches will be 21st December or potentially few days before to avoid having the likely last minute rush.
Quoted 4 lines
Given that we have decided to switch to a difference cadence, it would be prudent to work out when the best alignment of an 8-month cadence would be, rather than having it 8 months from now. If that means a one-off shorter or longer cycle for 4.12 then so be it.
The general holiday seasons are:
- Chinese new year (end of January ... mid of February), 2 weeks
- Eastern (end of March ... end of April), only a weak dependency?
- summer (August?), second half of July and first half of September as a weak dependency
- Christmas (end of December ... start of January), adding one week as a weak dependency
We don't like the planned release to be in or just before a holiday season. The period between last posting date and freeze should last 2 weeks, the freeze period should last 6 weeks.
In the diagram below I have used a 'X' for a major holiday season and a 'x' for a weak dependency. The lines below are possible release date variants just shifted by a weak each to show all possibilities.
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Xx.XXXXX...xxxx...........xxXXXXx..............X holidays
ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......
.ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR......
..ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.....
...ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR....
....ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR...
.....ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR..
......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.
.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR
R.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFF
FR.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFF
FFR.......ffFFFFFFR.......ffFFFFFFR.......ffFFFF
FFFR.......ffFFFFFFR.......ffFFFFFFR.......ffFFF
FFFFR.......ffFFFFFFR.......ffFFFFFFR.......ffFF
FFFFFR.......ffFFFFFFR.......ffFFFFFFR.......ffF
FFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......ff
fFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......f
We can rule out several variants with release dates just before or in a holiday season:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Xx.XXXXX...xxxx...........xxXXXXx..............X holidays
ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......
.ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR......
Best fit seems to be releasing in first half of March/July/November. The main clash seems to be Chinese new year in the freeze period, but avoiding that would mean we'd have to either move into Christmas or Eastern, or to use a schedule with varying periods.
Please remember that Chinese new year is only 2 weeks long (at varying dates) so only 2 weeks of the freeze period are hit. Next year the Chinese new year will be at February 5th.
For my 4.12 plan I've added some extra weeks between last posting date and release date to accommodate for the holiday seasons, resulting in my suggestion.
Juergen
_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xenproject.org/mailman/listinfo/xen-devel
Quoted 91 lines · Juergen Gross
Quoted 36 lines · Andrew Cooper
Quoted 29 lines · Julien Grall
Hi Juergen,
Quoted 19 lines · Juergen Gross
Its time to plan the Xen 4.12 release dates.
There have been concerns with the schedule of 6 months between releases, as this scheme is leading to too many supported versions of Xen at a time. The needed resources to backport bug fixes and security fixes as well as doing the tests for all those releases are a limiting factor to push out the current main release as well as point releases on time.
After some discussions at the Xen developer summit, on xen-devel and between the committers a slightly longer release cycle of 8 or 9 months was suggested.
With 18 months of full support and 36 months of security support the number of concurrent supported releases will be the same with either 8 or 9 months release cycles, so I have chosen an 8 month cycle for now. Having only 3 possible times in the year for a release will make it easier to avoid major holiday seasons. >
In case there is no objection I'm planning Xen 4.12 with:Quoted 2 lines
* Last posting date: December 14th, 2018
* Hard code freeze: January 11th, 2019In general, you would expect western people to slow down during Christmas period and have to deal with a pile of e-mail just after New Year. So I think, this is not very convenient period for a code freeze.
Quoted 5 lines
I usually take more holidays around Christmas and New Year. For this year, I will be on holidays from 21st December until the 13th January. This basically means my cut off for Arm patches will be 21st December or potentially few days before to avoid having the likely last minute rush.
Quoted 4 lines
Given that we have decided to switch to a difference cadence, it would be prudent to work out when the best alignment of an 8-month cadence would be, rather than having it 8 months from now. If that means a one-off shorter or longer cycle for 4.12 then so be it.
The general holiday seasons are:
- Chinese new year (end of January ... mid of February), 2 weeks
- Eastern (end of March ... end of April), only a weak dependency?
- summer (August?), second half of July and first half of September as a weak dependency
- Christmas (end of December ... start of January), adding one week as a weak dependencyWe don't like the planned release to be in or just before a holiday season. The period between last posting date and freeze should last 2 weeks, the freeze period should last 6 weeks.
In the diagram below I have used a 'X' for a major holiday season and a 'x' for a weak dependency. The lines below are possible release date variants just shifted by a weak each to show all possibilities.
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Xx.XXXXX...xxxx...........xxXXXXx..............X holidays
ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......
.ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR......
..ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.....
...ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR....
....ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR...
.....ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR..
......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.
.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR
R.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFF
FR.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFF
FFR.......ffFFFFFFR.......ffFFFFFFR.......ffFFFF
FFFR.......ffFFFFFFR.......ffFFFFFFR.......ffFFF
FFFFR.......ffFFFFFFR.......ffFFFFFFR.......ffFF
FFFFFR.......ffFFFFFFR.......ffFFFFFFR.......ffF
FFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......ff
fFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......fWe can rule out several variants with release dates just before or in a holiday season:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Xx.XXXXX...xxxx...........xxXXXXx..............X holidays
ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......
.ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR......Best fit seems to be releasing in first half of March/July/November. The main clash seems to be Chinese new year in the freeze period, but avoiding that would mean we'd have to either move into Christmas or Eastern, or to use a schedule with varying periods.
Quoted 7 lines
Please remember that Chinese new year is only 2 weeks long (at varying dates) so only 2 weeks of the freeze period are hit. Next year the Chinese new year will be at February 5th.
For my 4.12 plan I've added some extra weeks between last posting date and release date to accommodate for the holiday seasons, resulting in my suggestion.
Thanks for the detailed analysis Juregen. This seems good to me.
-George
_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xenproject.org/mailman/listinfo/xen-devel
Quoted 89 lines · George Dunlap
Quoted 88 lines · Juergen Gross
Quoted 34 lines · Andrew Cooper
Quoted 28 lines · Julien Grall
Hi Juergen,
Quoted 19 lines · Juergen Gross
Its time to plan the Xen 4.12 release dates.
There have been concerns with the schedule of 6 months between releases, as this scheme is leading to too many supported versions of Xen at a time. The needed resources to backport bug fixes and security fixes as well as doing the tests for all those releases are a limiting factor to push out the current main release as well as point releases on time.
After some discussions at the Xen developer summit, on xen-devel and between the committers a slightly longer release cycle of 8 or 9 months was suggested.
With 18 months of full support and 36 months of security support the number of concurrent supported releases will be the same with either 8 or 9 months release cycles, so I have chosen an 8 month cycle for now. Having only 3 possible times in the year for a release will make it easier to avoid major holiday seasons. >
In case there is no objection I'm planning Xen 4.12 with:Quoted 2 lines
* Last posting date: December 14th, 2018
* Hard code freeze: January 11th, 2019In general, you would expect western people to slow down during Christmas period and have to deal with a pile of e-mail just after New Year. So I think, this is not very convenient period for a code freeze.
Quoted 5 lines
I usually take more holidays around Christmas and New Year. For this year, I will be on holidays from 21st December until the 13th January. This basically means my cut off for Arm patches will be 21st December or potentially few days before to avoid having the likely last minute rush.
Quoted 4 lines
Given that we have decided to switch to a difference cadence, it would be prudent to work out when the best alignment of an 8-month cadence would be, rather than having it 8 months from now. If that means a one-off shorter or longer cycle for 4.12 then so be it.
The general holiday seasons are:
- Chinese new year (end of January ... mid of February), 2 weeks
- Eastern (end of March ... end of April), only a weak dependency?
- summer (August?), second half of July and first half of September as a weak dependency
- Christmas (end of December ... start of January), adding one week as a weak dependencyWe don't like the planned release to be in or just before a holiday season. The period between last posting date and freeze should last 2 weeks, the freeze period should last 6 weeks.
In the diagram below I have used a 'X' for a major holiday season and a 'x' for a weak dependency. The lines below are possible release date variants just shifted by a weak each to show all possibilities.
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Xx.XXXXX...xxxx...........xxXXXXx..............X holidays
ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......
.ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR......
..ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.....
...ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR....
....ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR...
.....ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR..
......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.
.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR
R.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFF
FR.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFF
FFR.......ffFFFFFFR.......ffFFFFFFR.......ffFFFF
FFFR.......ffFFFFFFR.......ffFFFFFFR.......ffFFF
FFFFR.......ffFFFFFFR.......ffFFFFFFR.......ffFF
FFFFFR.......ffFFFFFFR.......ffFFFFFFR.......ffF
FFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......ff
fFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......fWe can rule out several variants with release dates just before or in a holiday season:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Xx.XXXXX...xxxx...........xxXXXXx..............X holidays
ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......
.ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR......Best fit seems to be releasing in first half of March/July/November. The main clash seems to be Chinese new year in the freeze period, but avoiding that would mean we'd have to either move into Christmas or Eastern, or to use a schedule with varying periods.
Quoted 8 lines
Quoted 7 lines
Please remember that Chinese new year is only 2 weeks long (at varying dates) so only 2 weeks of the freeze period are hit. Next year the Chinese new year will be at February 5th.
For my 4.12 plan I've added some extra weeks between last posting date and release date to accommodate for the holiday seasons, resulting in my suggestion.
Thanks for the detailed analysis Juregen. This seems good to me.
I think it is also worth staying that we need to work on reducing the length of the hard freeze date, because as is visible from that diagram, its basically half the year.
~Andrew
_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xenproject.org/mailman/listinfo/xen-devel
Quoted 94 lines · Andrew Cooper
Quoted 93 lines · George Dunlap
Quoted 92 lines · Juergen Gross
Quoted 34 lines · Andrew Cooper
Quoted 28 lines · Julien Grall
Hi Juergen,
Quoted 19 lines · Juergen Gross
Its time to plan the Xen 4.12 release dates.
There have been concerns with the schedule of 6 months between releases, as this scheme is leading to too many supported versions of Xen at a time. The needed resources to backport bug fixes and security fixes as well as doing the tests for all those releases are a limiting factor to push out the current main release as well as point releases on time.
After some discussions at the Xen developer summit, on xen-devel and between the committers a slightly longer release cycle of 8 or 9 months was suggested.
With 18 months of full support and 36 months of security support the number of concurrent supported releases will be the same with either 8 or 9 months release cycles, so I have chosen an 8 month cycle for now. Having only 3 possible times in the year for a release will make it easier to avoid major holiday seasons. >
In case there is no objection I'm planning Xen 4.12 with:Quoted 2 lines
* Last posting date: December 14th, 2018
* Hard code freeze: January 11th, 2019In general, you would expect western people to slow down during Christmas period and have to deal with a pile of e-mail just after New Year. So I think, this is not very convenient period for a code freeze.
Quoted 5 lines
I usually take more holidays around Christmas and New Year. For this year, I will be on holidays from 21st December until the 13th January. This basically means my cut off for Arm patches will be 21st December or potentially few days before to avoid having the likely last minute rush.
Quoted 4 lines
Given that we have decided to switch to a difference cadence, it would be prudent to work out when the best alignment of an 8-month cadence would be, rather than having it 8 months from now. If that means a one-off shorter or longer cycle for 4.12 then so be it.
The general holiday seasons are:
- Chinese new year (end of January ... mid of February), 2 weeks
- Eastern (end of March ... end of April), only a weak dependency?
- summer (August?), second half of July and first half of September as a weak dependency
- Christmas (end of December ... start of January), adding one week as a weak dependencyWe don't like the planned release to be in or just before a holiday season. The period between last posting date and freeze should last 2 weeks, the freeze period should last 6 weeks.
In the diagram below I have used a 'X' for a major holiday season and a 'x' for a weak dependency. The lines below are possible release date variants just shifted by a weak each to show all possibilities.
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Xx.XXXXX...xxxx...........xxXXXXx..............X holidays
ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......
.ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR......
..ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.....
...ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR....
....ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR...
.....ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR..
......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.
.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR
R.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFF
FR.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFF
FFR.......ffFFFFFFR.......ffFFFFFFR.......ffFFFF
FFFR.......ffFFFFFFR.......ffFFFFFFR.......ffFFF
FFFFR.......ffFFFFFFR.......ffFFFFFFR.......ffFF
FFFFFR.......ffFFFFFFR.......ffFFFFFFR.......ffF
FFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......ff
fFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......fWe can rule out several variants with release dates just before or in a holiday season:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Xx.XXXXX...xxxx...........xxXXXXx..............X holidays
ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......
.ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR......Best fit seems to be releasing in first half of March/July/November. The main clash seems to be Chinese new year in the freeze period, but avoiding that would mean we'd have to either move into Christmas or Eastern, or to use a schedule with varying periods.
Please remember that Chinese new year is only 2 weeks long (at varying dates) so only 2 weeks of the freeze period are hit. Next year the Chinese new year will be at February 5th.
Quoted 8 lines
Quoted 4 lines
Quoted 3 lines
For my 4.12 plan I've added some extra weeks between last posting date and release date to accommodate for the holiday seasons, resulting in my suggestion.
Thanks for the detailed analysis Juregen. This seems good to me.
I think it is also worth staying that we need to work on reducing the length of the hard freeze date, because as is visible from that diagram, its basically half the year.
That diagram, however, is basically two years packed into one -- taken as only a single year it represents a 4-month cycle, not an 8-month cycle.
-George
_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xenproject.org/mailman/listinfo/xen-devel
Quoted 99 lines · George Dunlap
Quoted 97 lines · Andrew Cooper
Quoted 96 lines · George Dunlap
Quoted 95 lines · Juergen Gross
Quoted 34 lines · Andrew Cooper
Quoted 28 lines · Julien Grall
Hi Juergen,
Quoted 19 lines · Juergen Gross
Its time to plan the Xen 4.12 release dates.
There have been concerns with the schedule of 6 months between releases, as this scheme is leading to too many supported versions of Xen at a time. The needed resources to backport bug fixes and security fixes as well as doing the tests for all those releases are a limiting factor to push out the current main release as well as point releases on time.
After some discussions at the Xen developer summit, on xen-devel and between the committers a slightly longer release cycle of 8 or 9 months was suggested.
With 18 months of full support and 36 months of security support the number of concurrent supported releases will be the same with either 8 or 9 months release cycles, so I have chosen an 8 month cycle for now. Having only 3 possible times in the year for a release will make it easier to avoid major holiday seasons. >
In case there is no objection I'm planning Xen 4.12 with:Quoted 2 lines
* Last posting date: December 14th, 2018
* Hard code freeze: January 11th, 2019In general, you would expect western people to slow down during Christmas period and have to deal with a pile of e-mail just after New Year. So I think, this is not very convenient period for a code freeze.
Quoted 5 lines
I usually take more holidays around Christmas and New Year. For this year, I will be on holidays from 21st December until the 13th January. This basically means my cut off for Arm patches will be 21st December or potentially few days before to avoid having the likely last minute rush.
Quoted 4 lines
Given that we have decided to switch to a difference cadence, it would be prudent to work out when the best alignment of an 8-month cadence would be, rather than having it 8 months from now. If that means a one-off shorter or longer cycle for 4.12 then so be it.
The general holiday seasons are:
- Chinese new year (end of January ... mid of February), 2 weeks
- Eastern (end of March ... end of April), only a weak dependency?
- summer (August?), second half of July and first half of September as a weak dependency
- Christmas (end of December ... start of January), adding one week as a weak dependencyWe don't like the planned release to be in or just before a holiday season. The period between last posting date and freeze should last 2 weeks, the freeze period should last 6 weeks.
In the diagram below I have used a 'X' for a major holiday season and a 'x' for a weak dependency. The lines below are possible release date variants just shifted by a weak each to show all possibilities.
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Xx.XXXXX...xxxx...........xxXXXXx..............X holidays
ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......
.ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR......
..ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.....
...ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR....
....ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR...
.....ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR..
......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.
.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR
R.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFF
FR.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFF
FFR.......ffFFFFFFR.......ffFFFFFFR.......ffFFFF
FFFR.......ffFFFFFFR.......ffFFFFFFR.......ffFFF
FFFFR.......ffFFFFFFR.......ffFFFFFFR.......ffFF
FFFFFR.......ffFFFFFFR.......ffFFFFFFR.......ffF
FFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......ff
fFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......fWe can rule out several variants with release dates just before or in a holiday season:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Xx.XXXXX...xxxx...........xxXXXXx..............X holidays
ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......
.ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR......Best fit seems to be releasing in first half of March/July/November. The main clash seems to be Chinese new year in the freeze period, but avoiding that would mean we'd have to either move into Christmas or Eastern, or to use a schedule with varying periods.
Please remember that Chinese new year is only 2 weeks long (at varying dates) so only 2 weeks of the freeze period are hit. Next year the Chinese new year will be at February 5th.
For my 4.12 plan I've added some extra weeks between last posting date and release date to accommodate for the holiday seasons, resulting in my suggestion.
Quoted 7 lines
Quoted 4 lines
Quoted 1 line
Thanks for the detailed analysis Juregen. This seems good to me.
I think it is also worth staying that we need to work on reducing the length of the hard freeze date, because as is visible from that diagram, its basically half the year.
That diagram, however, is basically two years packed into one -- taken as only a single year it represents a 4-month cycle, not an 8-month cycle.
Oh - of course.
~Andrew
_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xenproject.org/mailman/listinfo/xen-devel
Quoted 94 lines · Andrew Cooper
Quoted 93 lines · George Dunlap
Quoted 92 lines · Juergen Gross
Quoted 34 lines · Andrew Cooper
Quoted 28 lines · Julien Grall
Hi Juergen,
Quoted 19 lines · Juergen Gross
Its time to plan the Xen 4.12 release dates.
There have been concerns with the schedule of 6 months between releases, as this scheme is leading to too many supported versions of Xen at a time. The needed resources to backport bug fixes and security fixes as well as doing the tests for all those releases are a limiting factor to push out the current main release as well as point releases on time.
After some discussions at the Xen developer summit, on xen-devel and between the committers a slightly longer release cycle of 8 or 9 months was suggested.
With 18 months of full support and 36 months of security support the number of concurrent supported releases will be the same with either 8 or 9 months release cycles, so I have chosen an 8 month cycle for now. Having only 3 possible times in the year for a release will make it easier to avoid major holiday seasons. >
In case there is no objection I'm planning Xen 4.12 with:Quoted 2 lines
* Last posting date: December 14th, 2018
* Hard code freeze: January 11th, 2019In general, you would expect western people to slow down during Christmas period and have to deal with a pile of e-mail just after New Year. So I think, this is not very convenient period for a code freeze.
Quoted 5 lines
I usually take more holidays around Christmas and New Year. For this year, I will be on holidays from 21st December until the 13th January. This basically means my cut off for Arm patches will be 21st December or potentially few days before to avoid having the likely last minute rush.
Quoted 4 lines
Given that we have decided to switch to a difference cadence, it would be prudent to work out when the best alignment of an 8-month cadence would be, rather than having it 8 months from now. If that means a one-off shorter or longer cycle for 4.12 then so be it.
The general holiday seasons are:
- Chinese new year (end of January ... mid of February), 2 weeks
- Eastern (end of March ... end of April), only a weak dependency?
- summer (August?), second half of July and first half of September as a weak dependency
- Christmas (end of December ... start of January), adding one week as a weak dependencyWe don't like the planned release to be in or just before a holiday season. The period between last posting date and freeze should last 2 weeks, the freeze period should last 6 weeks.
In the diagram below I have used a 'X' for a major holiday season and a 'x' for a weak dependency. The lines below are possible release date variants just shifted by a weak each to show all possibilities.
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Xx.XXXXX...xxxx...........xxXXXXx..............X holidays
ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......
.ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR......
..ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.....
...ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR....
....ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR...
.....ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR..
......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.
.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR
R.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFF
FR.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFF
FFR.......ffFFFFFFR.......ffFFFFFFR.......ffFFFF
FFFR.......ffFFFFFFR.......ffFFFFFFR.......ffFFF
FFFFR.......ffFFFFFFR.......ffFFFFFFR.......ffFF
FFFFFR.......ffFFFFFFR.......ffFFFFFFR.......ffF
FFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......ff
fFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......fWe can rule out several variants with release dates just before or in a holiday season:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Xx.XXXXX...xxxx...........xxXXXXx..............X holidays
ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......
.ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR......Best fit seems to be releasing in first half of March/July/November. The main clash seems to be Chinese new year in the freeze period, but avoiding that would mean we'd have to either move into Christmas or Eastern, or to use a schedule with varying periods.
Please remember that Chinese new year is only 2 weeks long (at varying dates) so only 2 weeks of the freeze period are hit. Next year the Chinese new year will be at February 5th.
Quoted 8 lines
Quoted 4 lines
Quoted 3 lines
For my 4.12 plan I've added some extra weeks between last posting date and release date to accommodate for the holiday seasons, resulting in my suggestion.
Thanks for the detailed analysis Juregen. This seems good to me.
I think it is also worth staying that we need to work on reducing the length of the hard freeze date, because as is visible from that diagram, its basically half the year.
No, it isn't. It can happen half the year, but in reality it is only every 9 months (so in one case out of three).
I believe that question is orthogonal to the one about time between releases. It basically boils down to the question when to branch the new release off the main trunk.
Juergen
_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xenproject.org/mailman/listinfo/xen-devel
Quoted 98 lines · Juergen Gross
Quoted 97 lines · Andrew Cooper
Quoted 96 lines · George Dunlap
Quoted 95 lines · Juergen Gross
Quoted 34 lines · Andrew Cooper
Quoted 28 lines · Julien Grall
Hi Juergen,
Quoted 19 lines · Juergen Gross
Its time to plan the Xen 4.12 release dates.
There have been concerns with the schedule of 6 months between releases, as this scheme is leading to too many supported versions of Xen at a time. The needed resources to backport bug fixes and security fixes as well as doing the tests for all those releases are a limiting factor to push out the current main release as well as point releases on time.
After some discussions at the Xen developer summit, on xen-devel and between the committers a slightly longer release cycle of 8 or 9 months was suggested.
With 18 months of full support and 36 months of security support the number of concurrent supported releases will be the same with either 8 or 9 months release cycles, so I have chosen an 8 month cycle for now. Having only 3 possible times in the year for a release will make it easier to avoid major holiday seasons. >
In case there is no objection I'm planning Xen 4.12 with:Quoted 2 lines
* Last posting date: December 14th, 2018
* Hard code freeze: January 11th, 2019In general, you would expect western people to slow down during Christmas period and have to deal with a pile of e-mail just after New Year. So I think, this is not very convenient period for a code freeze.
Quoted 5 lines
I usually take more holidays around Christmas and New Year. For this year, I will be on holidays from 21st December until the 13th January. This basically means my cut off for Arm patches will be 21st December or potentially few days before to avoid having the likely last minute rush.
Quoted 4 lines
Given that we have decided to switch to a difference cadence, it would be prudent to work out when the best alignment of an 8-month cadence would be, rather than having it 8 months from now. If that means a one-off shorter or longer cycle for 4.12 then so be it.
The general holiday seasons are:
- Chinese new year (end of January ... mid of February), 2 weeks
- Eastern (end of March ... end of April), only a weak dependency?
- summer (August?), second half of July and first half of September as a weak dependency
- Christmas (end of December ... start of January), adding one week as a weak dependencyWe don't like the planned release to be in or just before a holiday season. The period between last posting date and freeze should last 2 weeks, the freeze period should last 6 weeks.
In the diagram below I have used a 'X' for a major holiday season and a 'x' for a weak dependency. The lines below are possible release date variants just shifted by a weak each to show all possibilities.
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Xx.XXXXX...xxxx...........xxXXXXx..............X holidays
ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......
.ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR......
..ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.....
...ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR....
....ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR...
.....ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR..
......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.
.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR
R.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFFF
FR.......ffFFFFFFR.......ffFFFFFFR.......ffFFFFF
FFR.......ffFFFFFFR.......ffFFFFFFR.......ffFFFF
FFFR.......ffFFFFFFR.......ffFFFFFFR.......ffFFF
FFFFR.......ffFFFFFFR.......ffFFFFFFR.......ffFF
FFFFFR.......ffFFFFFFR.......ffFFFFFFR.......ffF
FFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......ff
fFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......fWe can rule out several variants with release dates just before or in a holiday season:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Xx.XXXXX...xxxx...........xxXXXXx..............X holidays
ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......
.ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR......Best fit seems to be releasing in first half of March/July/November. The main clash seems to be Chinese new year in the freeze period, but avoiding that would mean we'd have to either move into Christmas or Eastern, or to use a schedule with varying periods.
Please remember that Chinese new year is only 2 weeks long (at varying dates) so only 2 weeks of the freeze period are hit. Next year the Chinese new year will be at February 5th.
For my 4.12 plan I've added some extra weeks between last posting date and release date to accommodate for the holiday seasons, resulting in my suggestion.
Quoted 8 lines
Quoted 5 lines
Quoted 1 line
Thanks for the detailed analysis Juregen. This seems good to me.
I think it is also worth staying that we need to work on reducing the length of the hard freeze date, because as is visible from that diagram, its basically half the year.
No, it isn't. It can happen half the year, but in reality it is only every 9 months (so in one case out of three).
Aarg, of course this should be: every 8 months (so always skipping one case).
Juergen
_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xenproject.org/mailman/listinfo/xen-devel
Quoted 25 lines · George Dunlap
Quoted 20 lines · On Wed, Jul 25, 2018 at 10:22 AM, Juergen Gross <[email protected]…
fFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......f
We can rule out several variants with release dates just before or in a holiday season:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Xx.XXXXX...xxxx...........xxXXXXx..............X holidays
ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......
.ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR......Best fit seems to be releasing in first half of March/July/November. The main clash seems to be Chinese new year in the freeze period, but avoiding that would mean we'd have to either move into Christmas or Eastern, or to use a schedule with varying periods.
Please remember that Chinese new year is only 2 weeks long (at varying dates) so only 2 weeks of the freeze period are hit. Next year the Chinese new year will be at February 5th.
Quoted 7 lines
Quoted 3 lines
For my 4.12 plan I've added some extra weeks between last posting date and release date to accommodate for the holiday seasons, resulting in my suggestion.
Thanks for the detailed analysis Juregen. This seems good to me.
-George
This looks good to me also. To address Julien's concerns, we could also consider an earlier Last posting date/Hard code freeze date for Arm related code to work around Julien's holiday plans. I think this would be entirely OK and set expectations of contributors accordingly. But maybe this is not necessary if Julien and Stefano can agree a work split somehow.
Alternatively we could communicate absences of key reviewers say in November to set expectations of contributors for the final stretch of the release cycle. In other words, if a key reviewer is away, then contributors will need to get series into good shape before their reviewers go on vacation.
Regards
Lars
_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xenproject.org/mailman/listinfo/xen-devel
Quoted 42 lines · Lars Kurth
Quoted 27 lines
On 25 Jul 2018, at 12:24, George Dunlap <[email protected] <mailto:[email protected]>> wrote:
Quoted 20 lines · On Wed, Jul 25, 2018 at 10:22 AM, Juergen Gross <[email protected]…
fFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......f
We can rule out several variants with release dates just before or in a holiday season:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Xx.XXXXX...xxxx...........xxXXXXx..............X holidays ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR....... .ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR......
Best fit seems to be releasing in first half of March/July/November. The main clash seems to be Chinese new year in the freeze period, but avoiding that would mean we'd have to either move into Christmas or Eastern, or to use a schedule with varying periods.
Please remember that Chinese new year is only 2 weeks long (at varying dates) so only 2 weeks of the freeze period are hit. Next year the Chinese new year will be at February 5th.
Quoted 7 lines
Quoted 3 lines
For my 4.12 plan I've added some extra weeks between last posting date and release date to accommodate for the holiday seasons, resulting in my suggestion.
Thanks for the detailed analysis Juregen. This seems good to me.
-George
This looks good to me also. To address Julien's concerns, we could also consider an earlier Last posting date/Hard code freeze date for Arm related code to work around Julien's holiday plans. I think this would be entirely OK and set expectations of contributors accordingly. But maybe this is not necessary if Julien and Stefano can agree a work split somehow.
Quoted 5 lines
Alternatively we could communicate absences of key reviewers say in November to set expectations of contributors for the final stretch of the release cycle. In other words, if a key reviewer is away, then contributors will need to get series into good shape before their reviewers go on vacation.
I like that idea. Lets expand it to key persons (i.e. release manager, release technician, community manager, key reviewers).
Juergen
_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xenproject.org/mailman/listinfo/xen-devel
Quoted 47 lines · Juergen Gross
Quoted 42 lines · Lars Kurth
Quoted 27 lines
On 25 Jul 2018, at 12:24, George Dunlap <[email protected] <mailto:[email protected]>> wrote:
Quoted 20 lines · On Wed, Jul 25, 2018 at 10:22 AM, Juergen Gross <[email protected]…
fFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......f
We can rule out several variants with release dates just before or in a holiday season:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Xx.XXXXX...xxxx...........xxXXXXx..............X holidays
ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......
.ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR......Best fit seems to be releasing in first half of March/July/November. The main clash seems to be Chinese new year in the freeze period, but avoiding that would mean we'd have to either move into Christmas or Eastern, or to use a schedule with varying periods.
Please remember that Chinese new year is only 2 weeks long (at varying dates) so only 2 weeks of the freeze period are hit. Next year the Chinese new year will be at February 5th.
Quoted 7 lines
Quoted 3 lines
For my 4.12 plan I've added some extra weeks between last posting date and release date to accommodate for the holiday seasons, resulting in my suggestion.
Thanks for the detailed analysis Juregen. This seems good to me.
-George
This looks good to me also. To address Julien's concerns, we could also consider an earlier Last posting date/Hard code freeze date for Arm related code to work around Julien's holiday plans. I think this would be entirely OK and set expectations of contributors accordingly. But maybe this is not necessary if Julien and Stefano can agree a work split somehow.
Quoted 8 lines
Quoted 5 lines
Alternatively we could communicate absences of key reviewers say in November to set expectations of contributors for the final stretch of the release cycle. In other words, if a key reviewer is away, then contributors will need to get series into good shape before their reviewers go on vacation.
I like that idea. Lets expand it to key persons (i.e. release manager, release technician, community manager, key reviewers).
We should probably add this to the Release manager TODO list, such that we don't forget when the time comes. The same principle could apply to other holiday periods as well.
Lars
_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xenproject.org/mailman/listinfo/xen-devel
Quoted 53 lines · Lars Kurth
Quoted 53 lines · Juergen Gross
Quoted 47 lines · Lars Kurth
Quoted 27 lines
On 25 Jul 2018, at 12:24, George Dunlap <[email protected] <mailto:[email protected]>> wrote:
Quoted 20 lines · On Wed, Jul 25, 2018 at 10:22 AM, Juergen Gross <[email protected]…
fFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......f
We can rule out several variants with release dates just before or in a holiday season:
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Xx.XXXXX...xxxx...........xxXXXXx..............X holidays
ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR.......
.ffFFFFFFR.......ffFFFFFFR.......ffFFFFFFR......Best fit seems to be releasing in first half of March/July/November. The main clash seems to be Chinese new year in the freeze period, but avoiding that would mean we'd have to either move into Christmas or Eastern, or to use a schedule with varying periods.
Please remember that Chinese new year is only 2 weeks long (at varying dates) so only 2 weeks of the freeze period are hit. Next year the Chinese new year will be at February 5th.
Quoted 7 lines
Quoted 3 lines
For my 4.12 plan I've added some extra weeks between last posting date and release date to accommodate for the holiday seasons, resulting in my suggestion.
Thanks for the detailed analysis Juregen. This seems good to me.
-George
This looks good to me also. To address Julien's concerns, we could also consider an earlier Last posting date/Hard code freeze date for Arm related code to work around Julien's holiday plans. I think this would be entirely OK and set expectations of contributors accordingly. But maybe this is not necessary if Julien and Stefano can agree a work split somehow.
Alternatively we could communicate absences of key reviewers say in November to set expectations of contributors for the final stretch of the release cycle. In other words, if a key reviewer is away, then contributors will need to get series into good shape before their reviewers go on vacation.
Quoted 4 lines
Quoted 2 lines
I like that idea. Lets expand it to key persons (i.e. release manager, release technician, community manager, key reviewers).
We should probably add this to the Release manager TODO list, such that we don't forget when the time comes. The same principle could apply to other holiday periods as well.
I would rather tie that to the point in the release process. There might be planned vacations at other times, too.
I'll send a patch for the release management doc.
Juergen
_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xenproject.org/mailman/listinfo/xen-devel
Quoted 18 lines · Juergen Gross
Its time to plan the Xen 4.12 release dates.
There have been concerns with the schedule of 6 months between releases, as this scheme is leading to too many supported versions of Xen at a time. The needed resources to backport bug fixes and security fixes as well as doing the tests for all those releases are a limiting factor to push out the current main release as well as point releases on time.
After some discussions at the Xen developer summit, on xen-devel and between the committers a slightly longer release cycle of 8 or 9 months was suggested.
With 18 months of full support and 36 months of security support the number of concurrent supported releases will be the same with either 8 or 9 months release cycles, so I have chosen an 8 month cycle for now. Having only 3 possible times in the year for a release will make it easier to avoid major holiday seasons.
Quoted 8 lines
In case there is no objection I'm planning Xen 4.12 with:
* Last posting date: December 14th, 2018
* Hard code freeze: January 11th, 2019
* Release: March 7th, 2019Release of Xen 4.13 would then be early November 2019, 4.14 at early July 2020.
Given the holdidays season (it is not just Julien going on vacation but pretty much everybody), wouldn't it be better to move the hard code freeze by a couple of weeks? For instance Jan 25th? We can still keep the release date as Mar 7th, there should be still enough time?
_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xenproject.org/mailman/listinfo/xen-devel
Quoted 25 lines · Stefano Stabellini
Quoted 24 lines · Juergen Gross
Its time to plan the Xen 4.12 release dates.
There have been concerns with the schedule of 6 months between releases, as this scheme is leading to too many supported versions of Xen at a time. The needed resources to backport bug fixes and security fixes as well as doing the tests for all those releases are a limiting factor to push out the current main release as well as point releases on time.
After some discussions at the Xen developer summit, on xen-devel and between the committers a slightly longer release cycle of 8 or 9 months was suggested.
With 18 months of full support and 36 months of security support the number of concurrent supported releases will be the same with either 8 or 9 months release cycles, so I have chosen an 8 month cycle for now. Having only 3 possible times in the year for a release will make it easier to avoid major holiday seasons.
In case there is no objection I'm planning Xen 4.12 with:
* Last posting date: December 14th, 2018
* Hard code freeze: January 11th, 2019
* Release: March 7th, 2019
Quoted 7 lines
Quoted 2 lines
Release of Xen 4.13 would then be early November 2019, 4.14 at early July 2020.
Given the holdidays season (it is not just Julien going on vacation but pretty much everybody), wouldn't it be better to move the hard code freeze by a couple of weeks? For instance Jan 25th? We can still keep the release date as Mar 7th, there should be still enough time?
I don't think planning with a 6 week freeze period is a good idea. The last releases took longer than 2 months.
We could slip the complete release by 2 weeks, of course. In this case I'd move the last posting date to January. So something like:
* Last posting date: January 11th, 2019
* Hard code freeze: January 25th, 2019
* Release: March 21st, 2019
Risks for that schedule are:
- last posting date short after holiday season - is that really a problem?
- Chinese new year rather soon after start of freeze period
- planned release date rather close to eastern
Opinions?
Juergen
_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xenproject.org/mailman/listinfo/xen-devel
Quoted 41 lines · Juergen Gross
Quoted 25 lines · Stefano Stabellini
Quoted 24 lines · Juergen Gross
Its time to plan the Xen 4.12 release dates.
There have been concerns with the schedule of 6 months between releases, as this scheme is leading to too many supported versions of Xen at a time. The needed resources to backport bug fixes and security fixes as well as doing the tests for all those releases are a limiting factor to push out the current main release as well as point releases on time.
After some discussions at the Xen developer summit, on xen-devel and between the committers a slightly longer release cycle of 8 or 9 months was suggested.
With 18 months of full support and 36 months of security support the number of concurrent supported releases will be the same with either 8 or 9 months release cycles, so I have chosen an 8 month cycle for now. Having only 3 possible times in the year for a release will make it easier to avoid major holiday seasons.
In case there is no objection I'm planning Xen 4.12 with:
* Last posting date: December 14th, 2018
* Hard code freeze: January 11th, 2019
* Release: March 7th, 2019Quoted 7 lines
Quoted 2 lines
Release of Xen 4.13 would then be early November 2019, 4.14 at early July 2020.
Given the holdidays season (it is not just Julien going on vacation but pretty much everybody), wouldn't it be better to move the hard code freeze by a couple of weeks? For instance Jan 25th? We can still keep the release date as Mar 7th, there should be still enough time?
I don't think planning with a 6 week freeze period is a good idea. The last releases took longer than 2 months.
Quoted 6 lines
We could slip the complete release by 2 weeks, of course. In this case I'd move the last posting date to January. So something like:
* Last posting date: January 11th, 2019
* Hard code freeze: January 25th, 2019
* Release: March 21st, 2019
Another alternative would be to move the dates backwards rather than forward. The 4.12 development window effectively opened 21-06-18, so a last posting data and hard code freeze before Xmas should be OK. Then assume that there won't be RC's for at last 2 (maybe 3) weeks during the winter holidays. But as long as someone is there to keep an eye on OSSTEST and to do a force push and build an RC1 before Xmas that may be OK: but it would probably still be OK if RC1 slipped until just after New Years Eve.
Quoted 7 lines
Risks for that schedule are:
- last posting date short after holiday season - is that really a problem?
- Chinese new year rather soon after start of freeze period
- planned release date rather close to easternOpinions?
With this in mind. The only problem is that there will be Chinese New Year for some of the late to middle RCs ... Looking at possible RC dates
RC1: wk Jan 1st
RC2: wk Jan 8th
RC3: wk Jan 15th
RC4: wk Jan 22nd
RC5: wk Jan 29th
RC6: wk Feb 5th (Chinese New Year)
RC7: wk Feb 12th
RC8: wk Feb 19th
Lars
_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xenproject.org/mailman/listinfo/xen-devel
Quoted 49 lines · Lars Kurth
Quoted 42 lines
On 27 Jul 2018, at 08:51, Juergen Gross <[email protected] <mailto:[email protected]>> wrote:
Quoted 25 lines · Stefano Stabellini
Quoted 24 lines · Juergen Gross
Its time to plan the Xen 4.12 release dates.
There have been concerns with the schedule of 6 months between releases, as this scheme is leading to too many supported versions of Xen at a time. The needed resources to backport bug fixes and security fixes as well as doing the tests for all those releases are a limiting factor to push out the current main release as well as point releases on time.
After some discussions at the Xen developer summit, on xen-devel and between the committers a slightly longer release cycle of 8 or 9 months was suggested.
With 18 months of full support and 36 months of security support the number of concurrent supported releases will be the same with either 8 or 9 months release cycles, so I have chosen an 8 month cycle for now. Having only 3 possible times in the year for a release will make it easier to avoid major holiday seasons.
In case there is no objection I'm planning Xen 4.12 with:
* Last posting date: December 14th, 2018
* Hard code freeze: January 11th, 2019
* Release: March 7th, 2019Quoted 7 lines
Quoted 2 lines
Release of Xen 4.13 would then be early November 2019, 4.14 at early July 2020.
Given the holdidays season (it is not just Julien going on vacation but pretty much everybody), wouldn't it be better to move the hard code freeze by a couple of weeks? For instance Jan 25th? We can still keep the release date as Mar 7th, there should be still enough time?
I don't think planning with a 6 week freeze period is a good idea. The last releases took longer than 2 months.
Quoted 6 lines
We could slip the complete release by 2 weeks, of course. In this case I'd move the last posting date to January. So something like:
* Last posting date: January 11th, 2019
* Hard code freeze: January 25th, 2019
* Release: March 21st, 2019
Quoted 8 lines
Another alternative would be to move the dates backwards rather than forward. The 4.12 development window effectively opened 21-06-18, so a last posting data and hard code freeze before Xmas should be OK. Then assume that there won't be RC's for at last 2 (maybe 3) weeks during the winter holidays. But as long as someone is there to keep an eye on OSSTEST and to do a force push and build an RC1 before Xmas that may be
OK: but it would probably still be OK if RC1 slipped until just after New Years Eve.
You are neglecting that the reason for no RC directly after the freeze is normally due to bugs. And those need to be found and fixed by someone. So putting the freeze directly before a holiday season just makes the freeze longer without any major advantage.
Juergen
_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xenproject.org/mailman/listinfo/xen-devel
Quoted 59 lines · Juergen Gross
Quoted 49 lines · Lars Kurth
Quoted 42 lines
On 27 Jul 2018, at 08:51, Juergen Gross <[email protected] <mailto:[email protected]>> wrote:
Quoted 25 lines · Stefano Stabellini
Quoted 24 lines · Juergen Gross
Its time to plan the Xen 4.12 release dates.
There have been concerns with the schedule of 6 months between releases, as this scheme is leading to too many supported versions of Xen at a time. The needed resources to backport bug fixes and security fixes as well as doing the tests for all those releases are a limiting factor to push out the current main release as well as point releases on time.
After some discussions at the Xen developer summit, on xen-devel and between the committers a slightly longer release cycle of 8 or 9 months was suggested.
With 18 months of full support and 36 months of security support the number of concurrent supported releases will be the same with either 8 or 9 months release cycles, so I have chosen an 8 month cycle for now. Having only 3 possible times in the year for a release will make it easier to avoid major holiday seasons.
In case there is no objection I'm planning Xen 4.12 with:
* Last posting date: December 14th, 2018
* Hard code freeze: January 11th, 2019
* Release: March 7th, 2019Quoted 7 lines
Quoted 2 lines
Release of Xen 4.13 would then be early November 2019, 4.14 at early July 2020.
Given the holdidays season (it is not just Julien going on vacation but pretty much everybody), wouldn't it be better to move the hard code freeze by a couple of weeks? For instance Jan 25th? We can still keep the release date as Mar 7th, there should be still enough time?
I don't think planning with a 6 week freeze period is a good idea. The last releases took longer than 2 months.
Quoted 6 lines
We could slip the complete release by 2 weeks, of course. In this case I'd move the last posting date to January. So something like:
* Last posting date: January 11th, 2019
* Hard code freeze: January 25th, 2019
* Release: March 21st, 2019Quoted 8 lines
Another alternative would be to move the dates backwards rather than forward. The 4.12 development window effectively opened 21-06-18, so a last posting data and hard code freeze before Xmas should be OK. Then assume that there won't be RC's for at last 2 (maybe 3) weeks during the winter holidays. But as long as someone is there to keep an eye on OSSTEST and to do a force push and build an RC1 before Xmas that may be
OK: but it would probably still be OK if RC1 slipped until just after New Years Eve.
Quoted 4 lines
You are neglecting that the reason for no RC directly after the freeze is normally due to bugs. And those need to be found and fixed by someone. So putting the freeze directly before a holiday season just makes the freeze longer without any major advantage.
There is no silver bullet here, it is up to you. I'd say that given the current set of maintainers that we have, I think that overlapping with Chinese New Year is less damaging than overlapping with Christmas. So I'd move the dates backward by 2 weeks.
_______________________________________________
Xen-devel mailing list
[email protected]
https://lists.xenproject.org/mailman/listinfo/xen-devel
Quoted 65 lines · Stefano Stabellini
Quoted 59 lines · Juergen Gross
Quoted 49 lines · Lars Kurth
Quoted 42 lines
On 27 Jul 2018, at 08:51, Juergen Gross <[email protected] <mailto:[email protected]>> wrote:
Quoted 25 lines · Stefano Stabellini
Quoted 24 lines · Juergen Gross
Its time to plan the Xen 4.12 release dates.
There have been concerns with the schedule of 6 months between releases, as this scheme is leading to too many supported versions of Xen at a time. The needed resources to backport bug fixes and security fixes as well as doing the tests for all those releases are a limiting factor to push out the current main release as well as point releases on time.
After some discussions at the Xen developer summit, on xen-devel and between the committers a slightly longer release cycle of 8 or 9 months was suggested.
With 18 months of full support and 36 months of security support the number of concurrent supported releases will be the same with either 8 or 9 months release cycles, so I have chosen an 8 month cycle for now. Having only 3 possible times in the year for a release will make it easier to avoid major holiday seasons.
In case there is no objection I'm planning Xen 4.12 with:
* Last posting date: December 14th, 2018
* Hard code freeze: January 11th, 2019
* Release: March 7th, 2019Quoted 7 lines
Quoted 2 lines
Release of Xen 4.13 would then be early November 2019, 4.14 at early July 2020.
Given the holdidays season (it is not just Julien going on vacation but pretty much everybody), wouldn't it be better to move the hard code freeze by a couple of weeks? For instance Jan 25th? We can still keep the release date as Mar 7th, there should be still enough time?
I don't think planning with a 6 week freeze period is a good idea. The last releases took longer than 2 months.
Quoted 6 lines
We could slip the complete release by 2 weeks, of course. In this case I'd move the last posting date to January. So something like:
* Last posting date: January 11th, 2019
* Hard code freeze: January 25th, 2019
* Release: March 21st, 2019Quoted 8 lines
Another alternative would be to move the dates backwards rather than forward. The 4.12 development window effectively opened 21-06-18, so a last posting data and hard code freeze before Xmas should be OK. Then assume that there won't be RC's for at last 2 (maybe 3) weeks during the winter holidays. But as long as someone is there to keep an eye on OSSTEST and to do a force push and build an RC1 before Xmas that may be
OK: but it would probably still be OK if RC1 slipped until just after New Years Eve.Quoted 4 lines
You are neglecting that the reason for no RC directly after the freeze is normally due to bugs. And those need to be found and fixed by someone. So putting the freeze directly before a holiday season just makes the freeze longer without any major advantage.
Quoted 4 lines
There is no silver bullet here, it is up to you. I'd say that given the current set of maintainers that we have, I think that overlapping with Chinese New Year is less damaging than overlapping with Christmas. So I'd move the dates backward by 2 weeks.
Just for the records:
Via IRC we (Stefano and me) discussed the release schedule and now he is fine with my initial proposal:
* Last posting date: December 14th, 2018
* Hard code freeze: January 11th, 2019
* Release: March 7th, 2019
with the addendum that depending on vacation plans over Christmas e.g. patch series needing an Ack from arm maintainers might have an earlier last posting date.
Juergen