Is it a good idea to upgrade a package to a Release Candidate version, such as RC1, RC2 and so on ? I think no because:

1) Maybe the RC version is not stable enough.
2) Maybe the package's final version doesn't release when oe-core/meta-oe releases, I think that use an older but stable version is better than new RC version usually.

Signature · 3 lines
Thanks

Robert
#1 lore raw
Quoted 7 lines · Robert Yang

Is it a good idea to upgrade a package to a Release Candidate version, such as RC1, RC2 and so on ? I think no because:

1) Maybe the RC version is not stable enough.
2) Maybe the package's final version doesn't release when oe-core/meta-oe releases, I think that use an older but stable version is better than new RC version usually.

In general that's true, - qemu is the obvious recent exception because they should be releasing before we freeze and there were major fixes in the RC compared to the latest stable release.

Ross

#2 lore raw
Quoted 12 lines · Ross

On 28 July 2015 at 08:53, Robert Yang <[email protected]> wrote:
Is it a good idea to upgrade a package to a Release Candidate version,
such as RC1, RC2 and so on ? I think no because:

1) Maybe the RC version is not stable enough.
2) Maybe the package's final version doesn't release when oe-core/meta-oe releases, I think that use an older but
stable
version is better than new RC version usually.

Quoted 4 lines

In general that's true, - qemu is the obvious recent exception because they should be releasing before we freeze and there were major fixes in the RC compared to the latest stable release.

Agreed. If there is a pressing reason for an RC release which gives us more benefit than drawback, we can consider it on a case by case basis. With QEMU and the autobuilder issues we've been seeing, we decided we're better off being close to upstream right now.

Cheers,

Richard

#3 lore raw
Quoted 13 lines · Richard Purdie
Quoted 12 lines · Ross

On 28 July 2015 at 08:53, Robert Yang <[email protected]> wrote:
Is it a good idea to upgrade a package to a Release Candidate version,
such as RC1, RC2 and so on ? I think no because:

1) Maybe the RC version is not stable enough.
2) Maybe the package's final version doesn't release when oe-core/meta-oe releases, I think that use an older but
stable
version is better than new RC version usually.

Quoted 9 lines
Quoted 4 lines

In general that's true, - qemu is the obvious recent exception because they should be releasing before we freeze and there were major fixes in the RC compared to the latest stable release.

Agreed. If there is a pressing reason for an RC release which gives us more benefit than drawback, we can consider it on a case by case basis. With QEMU and the autobuilder issues we've been seeing, we decided we're better off being close to upstream right now.

Got it , thanks.

// Robert

Quoted 7 lines

Cheers,