Skip to contentSkip to conversation

B @ D 0.9 Gold Master

cip-dev Robert Marshall 2 participants 5 messages May 16, 2017 – May 22, 2017

lore
Share & tools
lore
#0 lore raw

We are about to close https://gitlab.com/cip-project/testing/issues/85 - B @ D 0.9 Gold Master declaration and thus we are declaring that the Gold Master for release 0.9 is ready and we will move onto the deployment phase (issue 86).

Thank you for your support, encouragement and even (especially?) the bug reports.

Robert

#1 lore raw

Hi,

Quoted 7 lines · Robert Marshall

We are about to close https://gitlab.com/cip-project/testing/issues/85 - B @ D 0.9 Gold Master declaration and thus we are declaring that the Gold Master for release 0.9 is ready and we will move onto the deployment phase (issue 86).

Thank you for your support, encouragement and even (especially?) the bug reports.

So the release of B at D is scheduled for May 23rd at 11:00 UTC Now we will concentrate in the following tasks:
* Deployment: #86 https://gitlab.com/cip-project/testing/issues/86
* Other release related tasks you can follow from #37
https://gitlab.com/cip-project/testing/issues/37

Best Regards

Signature · 3 lines
Agustin Benito Bethencourt
Principal Consultant - FOSS at Codethink
agustin.benito at codethink.co.uk
#2 lore raw

[cip-dev] B @ D 0.9 deployment (was Re: B @ D 0.9 Gold Master)

In reply to Robert Marshall
Quoted 8 lines · Robert Marshall

We are about to close https://gitlab.com/cip-project/testing/issues/85 - B @ D 0.9 Gold Master declaration and thus we are declaring that the Gold Master for release 0.9 is ready and we will move onto the deployment phase (issue 86).

Thank you for your support, encouragement and even (especially?) the bug reports.

The package and the sources are now deployed and we will close
https://gitlab.com/cip-project/testing/issues/86 - you can find the links to the downloadable files with that issue - and we will now move onto the release documentation -
https://gitlab.com/cip-project/testing/issues/37

The release of B at D is scheduled for May 23rd at 11:00 UTC.

Robert

#3 lore raw

[cip-dev] B @ D 0.9 deployment (was Re: B @ D 0.9 Gold Master)

Hi,

Quoted 11 lines · Robert Marshall
Quoted 8 lines · Robert Marshall

We are about to close https://gitlab.com/cip-project/testing/issues/85 - B @ D 0.9 Gold Master declaration and thus we are declaring that the Gold Master for release 0.9 is ready and we will move onto the deployment phase (issue 86).

Thank you for your support, encouragement and even (especially?) the bug reports.

Quoted 7 lines

The package and the sources are now deployed and we will close
https://gitlab.com/cip-project/testing/issues/86 - you can find the links to the downloadable files with that issue - and we will now move onto the release documentation -
https://gitlab.com/cip-project/testing/issues/37

The release of B at D is scheduled for May 23rd at 11:00 UTC.

Please do not spread the links on #86 before the release. The will be structured and described in the Download page and promoted on the Release Day.

Quoted 9 lines

Robert

_______________________________________________
cip-dev mailing list
cip-dev at lists.cip-project.org
https://lists.cip-project.org/mailman/listinfo/cip-dev

Signature · 3 lines
Agustin Benito Bethencourt
Principal Consultant - FOSS at Codethink
agustin.benito at codethink.co.uk
#4 lore raw

[cip-dev] B @ D 0.9 deployment (was Re: B @ D 0.9 Gold Master)

In reply to Robert Marshall

Hi,

Quoted 11 lines · Robert Marshall
Quoted 8 lines · Robert Marshall

We are about to close https://gitlab.com/cip-project/testing/issues/85 - B @ D 0.9 Gold Master declaration and thus we are declaring that the Gold Master for release 0.9 is ready and we will move onto the deployment phase (issue 86).

Thank you for your support, encouragement and even (especially?) the bug reports.

Quoted 7 lines

The package and the sources are now deployed and we will close
https://gitlab.com/cip-project/testing/issues/86 - you can find the links to the downloadable files with that issue - and we will now move onto the release documentation -
https://gitlab.com/cip-project/testing/issues/37

The release of B at D is scheduled for May 23rd at 11:00 UTC.

The license review process has not finished so we will wait for it before releasing the testing environment. I will let you know when is done and the new release date.

Best Regards

Signature · 3 lines
Agustin Benito Bethencourt
Principal Consultant - FOSS at Codethink
agustin.benito at codethink.co.uk