Current Dev Position: YP 2.7 M3 (New feature Freeze has begun.)

Next Deadline: YP 2.7 M3 Cutoff was Feb. 25, 2019

SWAT Team Rotation:

* SWAT lead is currently: Ross
* SWAT team rotation: Ross -> Chen on Mar. 1, 2019
* SWAT team rotation: Chen -> Armin on Mar. 8, 2019
* <https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team>
https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team

Key Status/Updates:

* We have now passed the feature freeze point for 2.7
* YP 2.7 M2 rc2 is out of QA and being readied for release. See:
<https://wiki.yoctoproject.org/wiki/WW07_-_2019-02-14_-_Full_Test_Cycle_2.7_
M2_RC2>
https://wiki.yoctoproject.org/wiki/WW07_-_2019-02-14_-_Full_Test_Cycle_2.7_M
2_RC2 and
<https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status#Milestone_2_-_
Target_Feb._1.2C_2019>
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status#Milestone_2_-_T
arget_Feb._1.2C_2019
* We now have resulttool, buildhistory and build-performance all
working with the autobuilder and will be using this as the primary QA mechanism going forward. More details can be found here:

<http://lists.openembedded.org/pipermail/openembedded-architecture/2019-Febr
uary/001591.html>
http://lists.openembedded.org/pipermail/openembedded-architecture/2019-Febru
ary/001591.html

* There were some serious usability issues found with multiconfig,
those have been fixed in master and thud.
* Various recipe upgrades made it in, thanks to all who contributed.
Several recipes also converted to meson including glib-2.0 and gdk-pixbuf.
* We now need to build M3 as we're past feature freeze point for 2.7.
Right now we're aware of the following things which ideally need to be resolved first:

* Bug 13178 "X server and matchbox desktop don't start up properly on
beaglebone" needs to be fixed
* Find the framebuffer problem with qemuarmv7 and switch to that
* Several ptest issues would be addressed (missing openssl tests, 3
timeouts)
* Arm build host issues identified and resolved

* It's unlikely we'll switch to virtgl by default for 2.7 due to lack
of testing from the community although the base patches for this have merged.

Planned Releases for YP 2.7:

* YP 2.7 M2 rc2 is out of QA.
* YP 2.7 M2 Release Target was Feb. 1, 2019
* YP 2.7 M3 Cutoff is Feb. 25, 2019
* YP 2.7 M3 Release Target is Mar. 8, 2019
* YP 2.7 M4 Cutoff is Apr. 1, 2019
* YP 2.7 M4 Release Target is Apr. 26, 2019

Planned upcoming dot releases:

* YP 2.5.3 (Sumo) will be targeted after YP 2.7 M2 is done.
* YP 2.5.4 (Sumo) will be targeted after YP 2.7 M4 is done.
* YP 2.6.2 (Thud) will be targeted after YP 2.5.4 is done.

Tracking Metrics:

* WDD 2415 (last week 2392) (
<https://wiki.yoctoproject.org/charts/combo.html>
https://wiki.yoctoproject.org/charts/combo.html)
* Poky Patch Metrics

* Total patches found: 1516 (last week 1527)
* Patches in the Pending State: 660 (44%) [last week 663 (43%)]

Key Status Links for YP:

<https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status>
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status

<https://wiki.yoctoproject.org/wiki/Yocto_2.7_Schedule>
https://wiki.yoctoproject.org/wiki/Yocto_2.7_Schedule

<https://wiki.yoctoproject.org/wiki/Yocto_2.7_Features>
https://wiki.yoctoproject.org/wiki/Yocto_2.7_Features

The Status reports are now stored on the wiki at:
<https://wiki.yoctoproject.org/wiki/Weekly_Status>
https://wiki.yoctoproject.org/wiki/Weekly_Status

[If anyone has suggestions for other information you'd like to see on this weekly status update, let us know!]

Thanks,

Stephen K. Jolley

Yocto Project Program Manager

* Cell: (208) 244-4460

* Email: [email protected]
<mailto:[email protected]>

#1 lore raw
Quoted 5 lines · On 2/26/19 7:58 AM, [email protected] wrote:

Current Dev Position: YP 2.7 M3 (New feature Freeze has begun.)

Next Deadline: YP 2.7 M3 Cutoff was Feb. 25, 2019

Quoted 8 lines

SWAT Team Rotation:

* SWAT lead is currently: Ross
* SWAT team rotation: Ross -> Chen on Mar. 1, 2019
* SWAT team rotation: Chen -> Armin on Mar. 8, 2019

I am going to be at LS on Monday March 10th and traveling on March 13. If this may be an issue, maybe rescheduling for a different week may be in order.
I personal don't this there will be an issue.

Quoted 20 lines

*

* https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team

Key Status/Updates:

* We have now passed the feature freeze point for 2.7
* YP 2.7 M2 rc2 is out of QA and being readied for release.  See:

    https://wiki.yoctoproject.org/wiki/WW07_-_2019-02-14_-_Full_Test_Cycle_2.7_M2_RC2
    and
    https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status#Milestone_2_-_Target_Feb._1.2C_2019

* We now have resulttool, buildhistory and build-performance all working with the autobuilder and will be using this as the primary QA mechanism going forward. More details can be found here:

http://lists.openembedded.org/pipermail/openembedded-architecture/2019-February/001591.html

Quoted 11 lines

* There were some serious usability issues found with multiconfig, those have been fixed in master and thud.
* Various recipe upgrades made it in, thanks to all who contributed. Several recipes also converted to meson including glib-2.0 and gdk-pixbuf.
* We now need to build M3 as we’re past feature freeze point for 2.7. Right now we’re aware of the following things which ideally need to be resolved first:
o Bug 13178 “X server and matchbox desktop don't start up properly on beaglebone” needs to be fixed

a patch was sent and  is in master.
http://git.yoctoproject.org/cgit/cgit.cgi/poky/commit/?id=4860914b3b5b38926ed6a80bb83a011d341ff2d8

- armin

Quoted 77 lines

o
o Find the framebuffer problem with qemuarmv7 and switch to that
o Several ptest issues would be addressed (missing openssl tests, 3 timeouts)
o Arm build host issues identified and resolved
* It’s unlikely we’ll switch to virtgl by default for 2.7 due to lack of testing from the community although the base patches for this have merged.

Planned Releases for YP 2.7:

* YP 2.7 M2 rc2 is out of QA.
* YP 2.7 M2 Release Target was Feb. 1, 2019
* YP 2.7 M3 Cutoff is Feb. 25, 2019
* YP 2.7 M3 Release Target is Mar. 8, 2019
* YP 2.7 M4 Cutoff is Apr. 1, 2019
* YP 2.7 M4 Release Target is Apr. 26, 2019

Planned upcoming dot releases:

* YP 2.5.3 (Sumo) will be targeted after YP 2.7 M2 is done.
* YP 2.5.4 (Sumo) will be targeted after YP 2.7 M4 is done.
* YP 2.6.2 (Thud) will be targeted after YP 2.5.4 is done.

Tracking Metrics:

* WDD 2415 (last week

    2392)(https://wiki.yoctoproject.org/charts/combo.html)

* Poky Patch Metrics
o Total patches found: 1516 (last week 1527)
o Patches in the Pending State: 660 (44%) [last week 663 (43%)]

Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.7_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.7_Features

The Status reports are now stored on the wiki at:
https://wiki.yoctoproject.org/wiki/Weekly_Status

[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]

Thanks,

*/Stephen K. Jolley/**//*

*Yocto Project Program Manager*

(    *Cell*:                (208) 244-4460

* *Email*:              [email protected]
<mailto:[email protected]>_