drm/nouveau: sched: avoid job races between entities
Subsystems (3)
PATCH 1/1 drm/nouveau: sched: avoid job races between entities
If a sched job depends on a dma-fence from a job from the same GPU scheduler instance, but a different scheduler entity, the GPU scheduler does only wait for the particular job to be scheduled, rather than for the job to fully complete. This is due to the GPU scheduler assuming that there is a scheduler instance per ring. However, the current implementation, in order to avoid arbitrary amounts of kthreads, has a single scheduler instance while scheduler entities represent rings.
As a workaround, set the DRM_SCHED_FENCE_DONT_PIPELINE for all out-fences in order to force the scheduler to wait for full job completion for dependent jobs from different entities and same scheduler instance.
There is some work in progress [1] to address the issues of firmware schedulers; once it is in-tree the scheduler topology in Nouveau should be re-worked accordingly.
[1] https://lore.kernel.org/dri-devel/[email protected]/
--- drivers/gpu/drm/nouveau/nouveau_sched.c | 22 ++++++++++++++++++++++ 1 file changed, 22 insertions(+)
drivers/gpu/drm/nouveau/nouveau_sched.c +22 -0
@@ -292,6 +292,28 @@ nouveau_job_submit(struct nouveau_job *job)if (job->sync) done_fence =dma_fence_get (job->done_fence); +/* If a sched job depends on a dma-fence from a job from the same GPU +* scheduler instance, but a different scheduler entity, the GPU +* scheduler does only wait for the particular job to be scheduled, +* rather than for the job to fully complete. This is due to the GPU +* scheduler assuming that there is a scheduler instance per ring. +* However, the current implementation, in order to avoid arbitrary +* amounts of kthreads, has a single scheduler instance while scheduler +* entities represent rings. +* +* As a workaround, set the DRM_SCHED_FENCE_DONT_PIPELINE for all +* out-fences in order to force the scheduler to wait for full job +* completion for dependent jobs from different entities and same +* scheduler instance. +* +* There is some work in progress [1] to address the issues of firmware +* schedulers; once it is in-tree the scheduler topology in Nouveau +* should be re-worked accordingly. +* +* [1] https://lore.kernel.org/dri-devel/[email protected]/ +*/ +set_bit (DRM_SCHED_FENCE_DONT_PIPELINE , &job->done_fence->flags); +if (job->ops->armed_submit) job->ops->armed_submit (job);
base-commit: 68132cc6d1bcbc78ade524c6c6c226de42139f0e
Signature · 1 line
2.41.0
Quoted 37 lines · Danilo Krummrich
If a sched job depends on a dma-fence from a job from the same GPU scheduler instance, but a different scheduler entity, the GPU scheduler does only wait for the particular job to be scheduled, rather than for the job to fully complete. This is due to the GPU scheduler assuming that there is a scheduler instance per ring. However, the current implementation, in order to avoid arbitrary amounts of kthreads, has a single scheduler instance while scheduler entities represent rings.
As a workaround, set the
DRM_SCHED_FENCE_DONT_PIPELINEfor all out-fences in order to force the scheduler to wait for full job completion for dependent jobs from different entities and same scheduler instance.There is some work in progress [1] to address the issues of firmware schedulers; once it is in-tree the scheduler topology in Nouveau should be re-worked accordingly.
[1]
https://lore.kernel.org/dri-devel/[email protected]/Signed-off-by Danilo Krummrich <[email protected]>--- drivers/gpu/drm/nouveau/nouveau_sched.c | 22 ++++++++++++++++++++++ 1 file changed, 22 insertions(+)drivers/gpu/drm/nouveau/nouveau_sched.c +1
-0@@ -292,6 +292,28 @@ nouveau_job_submit(struct nouveau_job *job)if (job->sync) done_fence =dma_fence_get (job->done_fence); +/* If a sched job depends on a dma-fence from a job from the same GPU
drivers/gpu/drm/nouveau/nouveau_sched.c nouveau_job_submit(struct nouveau_job *job) · line 297
Quoted 2 lines
drivers/gpu/drm/nouveau/nouveau_sched.c +2
-0+* scheduler instance, but a different scheduler entity, the GPU +* scheduler does only wait for the particular job to be scheduled,
s/does only wait/only waits/
+ * rather than for the job to fully complete. This is due to the GPU
Quoted 30 lines
drivers/gpu/drm/nouveau/nouveau_sched.c +3
-0+* scheduler assuming that there is a scheduler instance per ring. +* However, the current implementation, in order to avoid arbitrary +* amounts of kthreads, has a single scheduler instance while scheduler
drivers/gpu/drm/nouveau/nouveau_sched.c +8
-0+* entities represent rings. +* +* As a workaround, set the DRM_SCHED_FENCE_DONT_PIPELINE for all +* out-fences in order to force the scheduler to wait for full job +* completion for dependent jobs from different entities and same +* scheduler instance. +* +* There is some work in progress [1] to address the issues of firmware
drivers/gpu/drm/nouveau/nouveau_sched.c +4
-0+* schedulers; once it is in-tree the scheduler topology in Nouveau +* should be re-worked accordingly. +* +* [1] https://lore.kernel.org/dri-devel/[email protected]/
drivers/gpu/drm/nouveau/nouveau_sched.c +3
-0+*/ +set_bit (DRM_SCHED_FENCE_DONT_PIPELINE , &job->done_fence->flags); +if (job->ops->armed_submit) job->ops->armed_submit (job);base-commit:
68132cc6d1bcbc78ade524c6c6c226de42139f0e--