wireless-regdb: Update regulatory info for Australia (AU) for 2025

PATCH Applied Richard Huynh 2 participants 2 messages Oct 8, 2025 – Oct 9, 2025

lore
Share & tools
lore
#0 lore raw

PATCH v2 1/1 wireless-regdb: Update regulatory info for Australia (AU) for 2025

As of October 1 2025, a new class licence is in effect[1] Update the link and references in the comments to it

Also align the 915-928mhz block with the document

Additionally for the lower part of 6Ghz spectrum:
- Allow for EHT-320 as it complies with PSD limits
- Expand the upper range up to 6585 as permitted in new licence

[1] https://www.legislation.gov.au/Details/F2025L01047

---
 db.txt | 28 ++++++++++++++--------------
 1 file changed, 14 insertions(+), 14 deletions(-)
db.txt +14 -14
index 16bcb32..1d17271 100644
@@ -145,43 +145,43 @@ country AT: DFS-ETSI
 
 # Source:
 # 'Item' in the comments below refers to each numbered rule found at:
-# https://www.legislation.gov.au/Details/F2023C00524
+# https://www.legislation.gov.au/Details/F2025L01047 within Table 8
+# except for 5850-5875 which is found in Table 1.
 # Both DFS-ETSI and DFS-FCC are acceptable per AS/NZS 4268 Appendix B.
 # The EIRP for DFS bands can be increased by 3dB if TPC is implemented.
 # In order to allow 80MHz operation between 5650-5730MHz the upper boundary
 # of this more restrictive band has been shifted up by 5MHz from 5725MHz.
 country AU: DFS-ETSI
-	# Item 58
-	(915 - 920 @ 4), (1000 mW)
-	(920 - 928 @ 8), (1000 mW)
+	# Item 1
+	(915 - 928 @ 8), (1000 mW)
 
-	# Item 59
+	# Item 3 and 7
 	(2400 - 2483.5 @ 40), (4000 mW)
 
-	# Item 61
+	# Item 10
 	(5150 - 5250 @ 80), (200 mW), NO-OUTDOOR, AUTO-BW
 
-	# Item 62 (200 mW allowed if TPC is used)
+	# Item 11 (200 mW allowed if TPC is used)
 	(5250 - 5350 @ 80), (100 mW), NO-OUTDOOR, AUTO-BW, DFS
 
-	# Item 63(a) (1000 mW with TPC)
+	# Item 12(a) (1000 mW with TPC)
 	(5470 - 5600 @ 80), (500 mW), DFS
 
-	# Item 63(b) (1000 mW with TPC)
+	# Item 12(b) (1000 mW with TPC)
 	# The end is 5725 but we borrow 5 MHz from the following less restrictive band
 	# so we can get an 80 MHz channel.
 	(5650 - 5730 @ 80), (500 mW), DFS
 
-	# Item 60
+	# Item 9
 	(5730 - 5850 @ 80), (4000 mW), AUTO-BW
 
-	# Item 22
+	# Item 22 of Table 1
 	(5850 - 5875 @ 20), (25 mW), AUTO-BW
 
-	# Item 63AA (25 mW if outdoors)
-	(5925 - 6425 @ 160), (250 mW), NO-OUTDOOR
+	# Item 13 (25 mW if outdoors)
+	(5925 - 6585 @ 320), (250 mW), NO-OUTDOOR
 
-	# Item 65
+	# Item 18
 	(57000 - 71000 @ 2160), (20000 mW), NO-OUTDOOR
 
 country AW: DFS-ETSI
Signature · 1 line
2.51.0
Applied
#1 lore raw
Quoted 10 lines · Richard Huynh

As of October 1 2025, a new class licence is in effect[1] Update the link and references in the comments to it

Also align the 915-928mhz block with the document

Additionally for the lower part of 6Ghz spectrum:
- Allow for EHT-320 as it complies with PSD limits
- Expand the upper range up to 6585 as permitted in new licence

[...]

Applied to master in wens/wireless-regdb.git, thanks!

[1/1] wireless-regdb: Update regulatory info for Australia (AU) for 2025

      https://git.kernel.org/wens/wireless-regdb/c/75bedc589589

Best regards,

Signature · 1 line
Chen-Yu Tsai <[email protected]>