tracing/sched: add 'next_policy' to trace_sched_switch
PATCH v2 1/1 tracing/sched: add 'next_policy' to trace_sched_switch
In reply to a message not in the archiveFrom: gaoxiang17 <[email protected]>
Sometimes, when analyzing some real-time process issues, it is necessary to know the sched policy.
Show up in the trace as:
72.267374: sched_switch: prev_comm=grep prev_pid=67 prev_prio=19 prev_state=S ==> next_comm=cat next_pid=66 next_prio=120 next_policy=normal 72.267594: sched_switch: prev_comm=cat prev_pid=66 prev_prio=120 prev_state=R+ ==> next_comm=grep next_pid=67 next_prio=19 next_policy=RR 562.192567: sched_switch: prev_comm=grep prev_pid=85 prev_prio=19 prev_state=S ==> next_comm=cat next_pid=84 next_prio=120 next_policy=normal 562.192944: sched_switch: prev_comm=cat prev_pid=84 prev_prio=120 prev_state=R+ ==> next_comm=grep next_pid=85 next_prio=19 next_policy=FIFO
--- include/trace/events/sched.h | 15 +++++++++++++-- 1 file changed, 13 insertions(+), 2 deletions(-)
include/trace/events/sched.h +13 -2
@@ -234,6 +234,7 @@ TRACE_EVENT(sched_switch, __array( char, next_comm, TASK_COMM_LEN ) __field( pid_t, next_pid ) __field( int, next_prio ) + __field( unsigned int, next_policy ) ), TP_fast_assign(
@@ -244,10 +245,11 @@ TRACE_EVENT(sched_switch,memcpy (__entry->next_comm, next->comm,TASK_COMM_LEN ); __entry->next_pid = next->pid; __entry->next_prio = next->prio; + __entry->next_policy = next->policy;/* XXX SCHED_DEADLINE */ ), - TP_printk("prev_comm=%s prev_pid=%d prev_prio=%d prev_state=%s%s ==> next_comm=%s next_pid=%d next_prio=%d", + TP_printk("prev_comm=%s prev_pid=%d prev_prio=%d prev_state=%s%s ==> next_comm=%s next_pid=%d next_prio=%d next_policy=%s", __entry->prev_comm, __entry->prev_pid, __entry->prev_prio, (__entry->prev_state & (TASK_REPORT_MAX - 1)) ?
@@ -263,7 +265,16 @@ TRACE_EVENT(sched_switch,"R" , __entry->prev_state &TASK_REPORT_MAX ?"+" :"" , - __entry->next_comm, __entry->next_pid, __entry->next_prio) + __entry->next_comm, __entry->next_pid, __entry->next_prio, +__print_symbolic (__entry->next_policy, + { SCHED_NORMAL, "normal" }, + { SCHED_FIFO, "FIFO" }, + { SCHED_RR, "RR" }, + { SCHED_BATCH, "batch" }, + { SCHED_IDLE, "idle" }, + { SCHED_DEADLINE, "deadline" }, + { SCHED_EXT, "sched_ext"}) + ) );/*
Signature · 1 line
2.34.1
Steven Rostedt
maintainerQuoted 11 lines · On Tue, 26 Aug 2025 20:48:54 +0800 Xiang Gao <[email protected]> wrote:
From: gaoxiang17 <[email protected]>
Sometimes, when analyzing some real-time process issues, it is necessary to know the sched policy.
Show up in the trace as:
72.267374: sched_switch: prev_comm=grep prev_pid=67 prev_prio=19 prev_state=S ==> next_comm=cat next_pid=66 next_prio=120 next_policy=normal 72.267594: sched_switch: prev_comm=cat prev_pid=66 prev_prio=120 prev_state=R+ ==> next_comm=grep next_pid=67 next_prio=19 next_policy=RR 562.192567: sched_switch: prev_comm=grep prev_pid=85 prev_prio=19 prev_state=S ==> next_comm=cat next_pid=84 next_prio=120 next_policy=normal 562.192944: sched_switch: prev_comm=cat prev_pid=84 prev_prio=120 prev_state=R+ ==> next_comm=grep next_pid=85 next_prio=19 next_policy=FIFO
Peter,
Are you OK with extending the sched switch tracepoint?
-- Steve
Quoted 48 lines
Signed-off-by gaoxiang17 <[email protected]>--- include/trace/events/sched.h | 15 +++++++++++++-- 1 file changed, 13 insertions(+), 2 deletions(-)include/trace/events/sched.h +13
-2@@ -234,6 +234,7 @@ TRACE_EVENT(sched_switch, __array( char, next_comm, TASK_COMM_LEN ) __field( pid_t, next_pid ) __field( int, next_prio ) + __field( unsigned int, next_policy ) ), TP_fast_assign(@@ -244,10 +245,11 @@ TRACE_EVENT(sched_switch,memcpy (__entry->next_comm, next->comm,TASK_COMM_LEN ); __entry->next_pid = next->pid; __entry->next_prio = next->prio; + __entry->next_policy = next->policy;/* XXX SCHED_DEADLINE */ ), - TP_printk("prev_comm=%s prev_pid=%d prev_prio=%d prev_state=%s%s ==> next_comm=%s next_pid=%d next_prio=%d", + TP_printk("prev_comm=%s prev_pid=%d prev_prio=%d prev_state=%s%s ==> next_comm=%s next_pid=%d next_prio=%d next_policy=%s", __entry->prev_comm, __entry->prev_pid, __entry->prev_prio, (__entry->prev_state & (TASK_REPORT_MAX - 1)) ?@@ -263,7 +265,16 @@ TRACE_EVENT(sched_switch,"R" , __entry->prev_state &TASK_REPORT_MAX ?"+" :"" , - __entry->next_comm, __entry->next_pid, __entry->next_prio) + __entry->next_comm, __entry->next_pid, __entry->next_prio, +__print_symbolic (__entry->next_policy, + { SCHED_NORMAL, "normal" }, + { SCHED_FIFO, "FIFO" }, + { SCHED_RR, "RR" }, + { SCHED_BATCH, "batch" }, + { SCHED_IDLE, "idle" }, + { SCHED_DEADLINE, "deadline" }, + { SCHED_EXT, "sched_ext"}) + ) );/*
Quoted 15 lines · Steven Rostedt
Quoted 11 lines · On Tue, 26 Aug 2025 20:48:54 +0800 Xiang Gao <[email protected]> wrote:
From: gaoxiang17 <[email protected]>
Sometimes, when analyzing some real-time process issues, it is necessary to know the sched policy.
Show up in the trace as:
72.267374: sched_switch: prev_comm=grep prev_pid=67 prev_prio=19 prev_state=S ==> next_comm=cat next_pid=66 next_prio=120 next_policy=normal 72.267594: sched_switch: prev_comm=cat prev_pid=66 prev_prio=120 prev_state=R+ ==> next_comm=grep next_pid=67 next_prio=19 next_policy=RR 562.192567: sched_switch: prev_comm=grep prev_pid=85 prev_prio=19 prev_state=S ==> next_comm=cat next_pid=84 next_prio=120 next_policy=normal 562.192944: sched_switch: prev_comm=cat prev_pid=84 prev_prio=120 prev_state=R+ ==> next_comm=grep next_pid=85 next_prio=19 next_policy=FIFO
Quoted 3 lines
Peter,
Are you OK with extending the sched switch tracepoint?
I'm not convinced; this is a bit like whitespace patches, people will want their favourite field added and before you know it the thing will be fat as never before.
OTOH changing it will be yet another opportunity to find people that are not following the recommended practise. Someone will come forward and go complain we broke their shit or something.
Anyway, if we go touch it, you might as well go do it right and move prev_prio, next_prio and the polcy things into a u8 [*].
Also, I don't know why we have prev_prio, but if that is useful, shouldn't we also have prev_policy for consistenty sake?
That said, you can mostly guess the policy from the prio, I mean the distinction between fair/batch and rr/fifo gets lots, but you can readily tell the difference between the fair and rt and deadline tasks.
[*] I mean, we do use -1 for dl, and that'll map to 255 in u8, but we can't really use s8 since MAX_PRIO is 140. u8 is bits plenty, but just a bit weird *shurg*.
this way the event shrinks by 4 bytes, which is at least somewhat of a reason to do this.
Quoted 49 lines
Quoted 48 lines
Signed-off-by gaoxiang17 <[email protected]>--- include/trace/events/sched.h | 15 +++++++++++++-- 1 file changed, 13 insertions(+), 2 deletions(-)include/trace/events/sched.h +13
-2@@ -234,6 +234,7 @@ TRACE_EVENT(sched_switch, __array( char, next_comm, TASK_COMM_LEN ) __field( pid_t, next_pid ) __field( int, next_prio ) + __field( unsigned int, next_policy ) ), TP_fast_assign(@@ -244,10 +245,11 @@ TRACE_EVENT(sched_switch,memcpy (__entry->next_comm, next->comm,TASK_COMM_LEN ); __entry->next_pid = next->pid; __entry->next_prio = next->prio; + __entry->next_policy = next->policy;/* XXX SCHED_DEADLINE */ ), - TP_printk("prev_comm=%s prev_pid=%d prev_prio=%d prev_state=%s%s ==> next_comm=%s next_pid=%d next_prio=%d", + TP_printk("prev_comm=%s prev_pid=%d prev_prio=%d prev_state=%s%s ==> next_comm=%s next_pid=%d next_prio=%d next_policy=%s", __entry->prev_comm, __entry->prev_pid, __entry->prev_prio, (__entry->prev_state & (TASK_REPORT_MAX - 1)) ?@@ -263,7 +265,16 @@ TRACE_EVENT(sched_switch,"R" , __entry->prev_state &TASK_REPORT_MAX ?"+" :"" , - __entry->next_comm, __entry->next_pid, __entry->next_prio) + __entry->next_comm, __entry->next_pid, __entry->next_prio, +__print_symbolic (__entry->next_policy, + { SCHED_NORMAL, "normal" }, + { SCHED_FIFO, "FIFO" }, + { SCHED_RR, "RR" }, + { SCHED_BATCH, "batch" }, + { SCHED_IDLE, "idle" }, + { SCHED_DEADLINE, "deadline" }, + { SCHED_EXT, "sched_ext"}) + ) );/*
Quoted 3 lines · Peter Zijlstra
That said, you can mostly guess the policy from the prio, I mean the distinction between fair/batch and rr/fifo gets lots, but you can readily tell the difference between the fair and rt and deadline tasks.
FWIW mixing RR and FIFO tasks is asking for pain, adding tracing information isn't going to help you restore your sanity.